Chattahoochee Energy Facility
3461 Hollingswarth Ferry Rd, Franklin, GA 30217Plant Summary Information
Chattahoochee Energy Facility is ranked #10 out of 243 power plants in Georgia in terms of total annual net electricity generation.
Chattahoochee Energy Facility is comprised of 3 generators and generated 463.9 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Chattahoochee Energy Facility |
---|---|
Utility Name | Oglethorpe Power Corporation |
Location | Heard County, GA |
Initial Operation Date | February 2003 |
Last Update | Jan 2025 |
Annual Generation | 2.8 TWh |
Annual Consumption | 21.8 M MMBtu |
Ranked #414 out of 11,979 Power Plants Nationwide | |
Ranked #253 out of 2,255 Natural Gas Power Plants Nationwide | |
Ranked #10 out of 243 Georgia Power Plants | |
Ranked #6 out of 47 Georgia Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Chattahoochee Energy Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Chattahoochee Energy Facility.
Monthly Net Generation for Chattahoochee Energy Facility
Chattahoochee Energy Facility Details
Summary Information | |
---|---|
Plant Name | Chattahoochee Energy Facility (7917) |
Plant Address | 3461 Hollingswarth Ferry Rd, Franklin, GA 30217 |
Utility | Oglethorpe Power Corporation (13994) |
Latitude, Longitude | 33.4072, -85.0386 |
Generation Dates on File | Feb 2003 to Jan 2025 |
Initial Operation Date | February 2003 |
Annual Generation | 2.8 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Chattahoochee River |
Ash Impoundment | |
Transmission / Distribution Owner | Georgia Transmission Corp (7197) GA |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | TRANSCONTINENTAL GAS PIPELINE |
Natural Gas Storage | No |
Generator 1 Details Operating February 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | 2224 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 145.5 MW |
Winter Capacity | 169.5 MW |
Minimum Load | 65 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 2 Details Operating February 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | 2224 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 141.5 MW |
Winter Capacity | 167.5 MW |
Minimum Load | 130 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Generator 3 Details Operating February 2003
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | 2224 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 187.7 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 179 MW |
Winter Capacity | 189 MW |
Minimum Load | 130 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | February 2003 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Chattahoochee Energy Facility Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#243 | Kleen Energy Systems Project | Middletown, CT | 2.9 TWh |
#244 | Nelson Energy Center | Rock Falls, IL | 2.9 TWh |
#245 | Northeastern | Oologah, OK | 4.2 TWh |
#246 | Eastman Cogeneration Facility | Longview, TX | 2.9 TWh |
#247 | Empire Generating Co LLC | Rensselaer, NY | 2.9 TWh |
#248 | Currant Creek | Mona, UT | 2.8 TWh |
#249 | Silverhawk | North Las Vegas, NV | 2.8 TWh |
#250 | GREC | Chouteau, OK | 3.4 TWh |
#251 | Gateway Generating Station | Antioch, CA | 2.8 TWh |
#252 | Port Westward | Clatskanie, OR | 2.8 TWh |
#254 | Gulf Clean Energy Center | Pensacola, FL | 2.8 TWh |
#255 | Attala | Sallis, MS | 2.7 TWh |
#256 | Colusa Generating Station | Maxwell, CA | 2.7 TWh |
#257 | South Point Energy Center | Mohave Valley, AZ | 2.7 TWh |
#258 | Bridgeport Energy Project | Bridgeport, CT | 2.7 TWh |
#259 | ANP Bellingham Energy Project | Bellingham, MA | 2.7 TWh |
#260 | Sabine River Operations | Orange, TX | 2.7 TWh |
#261 | Hobbs Generating Station | Hobbs, NM | 2.7 TWh |
#262 | Riverside (MN) | Minneapolis, MN | 2.6 TWh |
#263 | R D Morrow | Purvis, MS | 2.6 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Chattahoochee Energy Facility.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Atlanta Falcons Solar | Atlanta, GA | 1.1 GWh | 43.9 mi |
Camp Solar Plant | Woodbury, GA | 3.2 GWh | 41.9 mi |
Greenville | Greenville, GA | 1.4 GWh | 31.2 mi |
Harris Dam | Lineville, AL | 128.9 GWh | 34.9 mi |
Hawk Road Facility | Franklin, GA | 569.4 GWh | 4.3 mi |
Jack McDonough | Smyrna, GA | 17.7 TWh | 43.3 mi |
Kimberly-Clark Solar | LaGrange, GA | 2.7 GWh | 28.1 mi |
LaFayette Solar Farm | LaFayette, AL | 165.2 GWh | 41.9 mi |
MAS ASB Cogen Plant | Atlanta, GA | 39.9 GWh | 40.9 mi |
Meriwether Jackson | Machester, GA | 5.9 GWh | 43.1 mi |
Rockmart | Rockmart, GA | 5.5 GWh | 42 mi |
Sewell Creek Energy | Cedartown, GA | 425.2 GWh | 39.8 mi |
Tenaska Georgia Generation Facility | Franklin, GA | 35.0 GWh | 4.5 mi |
Troup RC50 | Pine Mountain, GA | 4.6 GWh | 37 mi |
Troup RC50 II | Pine Mountain, GA | 2.9 GWh | 36.1 mi |
Turnipseed Solar, LLC | Douglasville, GA | 5.2 GWh | 28.9 mi |
Wansley Combined Cycle | Franklin, GA | 7.8 TWh | 0.1 mi |
Wansley Unit 9 | Franklin, GA | 3.4 TWh | 0.1 mi |
West Point (GA) | West Point, GA | 198.7 GWh | 34.9 mi |
Yates | Newnan, GA | 2.2 TWh | 8.9 mi |