Century
301 Commercial St, Blairsburg, IA 50034Plant Summary Information
Century is ranked #42 out of 271 power plants in Iowa in terms of total annual net electricity generation.
Century generated 166.3 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Century |
---|---|
Utility Name | MidAmerican Energy Co |
Location | Hamilton County, IA |
Initial Operation Date | September 2005 |
Last Update | Dec 2023 |
Annual Generation | 570.0 GWh |
Annual Consumption | 2.2 M MMBtu |
Ranked #1,144 out of 11,835 Power Plants Nationwide | |
Ranked #278 out of 1,343 Wind Power Plants Nationwide | |
Ranked #42 out of 271 Iowa Power Plants | |
Ranked #30 out of 123 Iowa Wind Power Plants | |
Fuel Types | Wind |
Map of Century
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Century.
Monthly Net Generation for Century
Century Details
Summary Information | |
---|---|
Plant Name | Century (56252) |
Plant Address | 301 Commercial St, Blairsburg, IA 50034 |
Utility | MidAmerican Energy Co (12341) |
Latitude, Longitude | 42.5644, -93.6369 |
Generation Dates on File | Jul 2005 to Dec 2023 |
Initial Operation Date | September 2005 |
Annual Generation | 570.0 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | MRO |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | MidAmerican Energy Co (12341) IA |
Grid Voltage | 161.00 kV |
Energy Storage | No |
Generator CWF Details Operating September 2005
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
RTO ISO LMP Node Designation | MEC.Century_1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | MEC.Century_1 |
Nameplate Capacity | 150 MW |
Summer Capacity | 150 MW |
Winter Capacity | 150 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2005 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 100 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 100 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.5-82.5 |
Design Wind Speed | 16.8 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 213 |
Generator CWF2 Details Operating December 2007
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 35 MW |
Summer Capacity | 35 MW |
Winter Capacity | 35 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2007 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
---|---|
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 35 |
Planned New Prime Mover | WT |
Planned Energy Source | WND |
Planned New Nameplate Capacity | 35 MW |
Planned Repower | November 2024 |
Other Planned Modifications | No |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 35 |
---|---|
Predominant Turbine Manufacturer | Mitsubishi |
Predominant Turbine Model Number | MWT-1000A |
Design Wind Speed | 16.8 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 197 |
Generator CWF3 Details Operating December 2007
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 16.2 MW |
Summer Capacity | 16.2 MW |
Winter Capacity | 16.2 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2007 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 10 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 10 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.6-87 |
Design Wind Speed | 16.8 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 263 |
Century Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#268 | Tatanka Ridge | Toronto, SD | 581.5 GWh |
#269 | Minonk Wind Farm | Minonk, IL | 580.4 GWh |
#270 | Cranell Wind Farm LLC | TBD, TX | 577.6 GWh |
#271 | North Hurlburt Wind LLC | Arlington, OR | 574.5 GWh |
#272 | Wildcat Creek Wind Farm LLC | Gainesville, TX | 574.4 GWh |
#273 | Solano Wind | Rio Vista, CA | 574.4 GWh |
#274 | English Farms | Montezuma, IA | 573.5 GWh |
#275 | FPL Energy Story Wind LLC | Zearing, IA | 572.6 GWh |
#276 | Weatherford Wind Energy Center | Weatherford, OK | 571.7 GWh |
#277 | Limon Wind I | Limon, CO | 571.6 GWh |
#279 | Alta Farms II Wind Project, LLC | Clinton, IL | 568.9 GWh |
#280 | Blue Canyon Windpower II | Carnegie, OK | 568.5 GWh |
#281 | Pilot Hill Wind Farm | Herscher, IL | 568.0 GWh |
#282 | Windy Flats Wind Project | Centerville, WA | 567.8 GWh |
#283 | Blue Cloud Wind Energy LLC | Sudan, TX | 567.7 GWh |
#284 | Colorado Green Holdings LLC | Lamar, CO | 566.9 GWh |
#285 | Wheatridge Hybrid | Morrow, OR | 688.0 GWh |
#286 | Bishop Hill Energy LLC | Cambridge, IL | 564.1 GWh |
#287 | Stella Wind Farm | Armstrong, TX | 563.3 GWh |
#288 | FPL Energy Ashtabula Wind LLC | Luverne, ND | 561.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Century.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Cerro Gordo Wind Farm | Union, IA | 176.4 GWh | 35.6 mi |
Dayton (IA) | Dayton, IA | 15.0 MWh | 30.5 mi |
FPL Energy Story Wind LLC | Zearing, IA | 572.6 GWh | 36.8 mi |
Franklin County Solar | Hampton, IA | 13.6 GWh | 24.4 mi |
Franklin County Wind Farm | Iowa Falls, IA | 236.2 GWh | 15.6 mi |
Garden Wind LLC | Zearing, IA | 374.8 GWh | 27.1 mi |
Great Pathfinder Wind | Stratford, IA | 785.6 GWh | 27.1 mi |
Hancock County Wind Energy Center | Garner, IA | 261.0 GWh | 33.7 mi |
Hawkeye Power Partners LLC | Garner, IA | 166.1 GWh | 34.3 mi |
Holliday Creek Solar | Fort Dodge, IA | 202.0 GWh | 23.7 mi |
Leonardo Wind 1 LLC | Alden, IA | 11.2 GWh | 14.4 mi |
Lundgren Wind Project | Otho, IA | 805.8 GWh | 31.5 mi |
NCAH Central Utility Plant | Ames, IA | 14.9 GWh | 35.9 mi |
POET Biorefining - Jewell | Jewell, IA | 21.3 GWh | 16.4 mi |
Story City | Story City, IA | 233.0 MWh | 26.2 mi |
Story City Wind Project | Story City, IA | 2.6 GWh | 24.7 mi |
Webster City | Webster City, IA | 2.0 GWh | 11.1 mi |
Wellsburg Wind Project | Wellsburg, IA | 441.8 GWh | 36.2 mi |
Whispering Willow North | Latimer, IA | 787.7 GWh | 18.3 mi |
Whispering Willow Wind Farm - East | Iowa Falls, IA | 459.4 GWh | 22.4 mi |