Campbell Hill Windpower
1068 Cole Creek Road, Glenrock, WY 82637Plant Summary Information
Campbell Hill Windpower is ranked #25 out of 73 power plants in Wyoming in terms of total annual net electricity generation.
Campbell Hill Windpower generated 103.0 GWh during the 3-month period between October 2024 to January 2025.
Plant Name | Campbell Hill Windpower |
---|---|
Utility Name | Duke Energy Renewables Services |
Location | Converse County, WY |
Initial Operation Date | December 2009 |
Last Update | Jan 2025 |
Annual Generation | 287.7 GWh |
Annual Consumption | 1.1 M MMBtu |
Ranked #1,920 out of 11,979 Power Plants Nationwide | |
Ranked #585 out of 1,359 Wind Power Plants Nationwide | |
Ranked #25 out of 73 Wyoming Power Plants | |
Ranked #13 out of 31 Wyoming Wind Power Plants | |
Fuel Types | Wind |
Previous Operator |
Duke Energy DEGS Campbell Hill (2013 to 2021) Duke Energy Renewables Services (2022 to 2023) |
Map of Campbell Hill Windpower
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Campbell Hill Windpower.
Monthly Net Generation for Campbell Hill Windpower
Campbell Hill Windpower Details
Summary Information | |
---|---|
Plant Name | Campbell Hill Windpower (57090) |
Plant Address | 1068 Cole Creek Road, Glenrock, WY 82637 |
Utility | Duke Energy Renewables Services (65411) |
Latitude, Longitude | 43.01455, -105.999 |
Generation Dates on File | Dec 2009 to Jan 2025 |
Initial Operation Date | December 2009 |
Annual Generation | 287.7 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | PacifiCorp (14354) WY |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator CHWF Details Operating December 2009
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 99 MW |
Summer Capacity | 99 MW |
Winter Capacity | 99 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Turbines/Hydrokinetic Buoys | 66 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 66 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.5 SLE |
Design Wind Speed | 15 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 272 |
Campbell Hill Windpower Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#575 | Minco Wind II, LLC | Minco, OK | 296.5 GWh |
#576 | Palouse | Oakesdale, WA | 294.9 GWh |
#577 | Blue Canyon Windpower VI LLC | Carnegie, OK | 294.7 GWh |
#578 | Shiloh IV Wind Project LLC | Birds Landing, CA | 294.4 GWh |
#579 | Dakota Range Wind | SD | 294.3 GWh |
#580 | MinnDakota Wind LLC | Ivanhoe, MN | 294.1 GWh |
#581 | Saratoga Wind Farm | Lime Springs, IA | 292.5 GWh |
#582 | Buffalo Gap 3 Wind Farm | Nolan, TX | 292.1 GWh |
#583 | Wheatridge 1 | Lexington, OR | 290.1 GWh |
#584 | Elk River Wind | Beaumont, KS | 287.8 GWh |
#586 | Number Three Wind Project | Lowville, NY | 286.6 GWh |
#587 | Stillwater Wind, LLC | Reed Point, MT | 284.6 GWh |
#588 | South Fork Wind | East Hampton, NY | 283.3 GWh |
#589 | Crane Creek Wind Energy Center | Riceville, IA | 282.2 GWh |
#590 | Mountain View I & II | North Palm Springs, CA | 279.7 GWh |
#591 | Fenton Wind Farm | Chandler, MN | 278.1 GWh |
#592 | NaturEner Glacier Wind Energy 2 | Ethridge, MT | 277.1 GWh |
#593 | New Creek Wind | New Creek, WV | 276.6 GWh |
#594 | Hancock County Wind Energy Center | Garner, IA | 276.3 GWh |
#595 | Red Barn Energy | Montfort, WI | 276.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Campbell Hill Windpower.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alcova | Alcova, WY | 68.1 GWh | 48.6 mi |
Anticline Wind | Casper, WY | 53.8 GWh | 19.8 mi |
Barber Creek | Gillette, WY | 359.0 MWh | 50.2 mi |
Casper Wind Farm | Evansville, WY | 5.7 GWh | 14.4 mi |
Cedar Springs I | Douglas, WY | 752.1 GWh | 26.6 mi |
Cedar Springs II | Douglas, WY | 622.5 GWh | 32.2 mi |
Cedar Springs III | Douglas, WY | 525.6 GWh | 21.4 mi |
Cedar Springs Wind IV | Douglas, WY | 8.7 GWh | 15.7 mi |
Dave Johnston | Glen Rock, WY | 4.0 TWh | 16.6 mi |
Dunlap | Medicine Bow, WY | 432.0 GWh | 67.6 mi |
Fremont Canyon | Alcova, WY | 176.3 GWh | 54.9 mi |
Glendo | Glendo, WY | 80.6 GWh | 65.1 mi |
Glenrock | Glenrock, WY | 314.1 GWh | 8.3 mi |
Hartzog | Wright, WY | 318.0 MWh | 61 mi |
Kortes | Sinclair, WY | 146.2 GWh | 73.4 mi |
Pioneer Wind Park, LLC | Glenrock, WY | 226.3 GWh | 20.9 mi |
Rolling Hills | Glenrock, WY | 187.8 GWh | 7.9 mi |
Seminoe | Sinclair, WY | 140.7 GWh | 75.2 mi |
TB Flats | Medicine Bow, WY | 1.4 TWh | 59.1 mi |
Top of the World Windpower Project | Glenrock, WY | 379.8 GWh | 12.3 mi |