Camas Solar Project

4561 No 6 Road, Ellensburg, WA 98926

Plant Summary Information

Camas Solar Project is ranked #5 out of 8 solar farms in Washington in terms of total annual net electricity generation.

Camas Solar Project generated 1.1 GWh during the 3-month period between September 2023 to December 2023.

Plant NameCamas Solar Project
Utility NameGreenbacker Renewable Energy Corporation
LocationKittitas County, WA
Initial Operation DateJune 2022
Last Update Dec 2023
Annual Generation 10.3 GWh
Annual Consumption 35.5 k MMBtu
Ranked #5,863 out of 11,852 Power Plants Nationwide
Ranked #1,505 out of 5,655 Solar Power Plants Nationwide
Ranked #112 out of 134 Washington Power Plants
Ranked #5 out of 8 Washington Solar Power Plants
Fuel Types Solar
Previous Operator TUUSSO Energy, LLC (2018 to 2020)
Greenbacker Renewable Energy Corporation (2021 to 2023)

Map of Camas Solar Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Camas Solar Project.

Create Your Account Today

Monthly Net Generation for Camas Solar Project

Camas Solar Project Details

Summary Information
Plant NameCamas Solar Project (62071)
Plant Address4561 No 6 Road, Ellensburg, WA 98926
UtilityGreenbacker Renewable Energy Corporation (60025)
Latitude, Longitude46.95931, -120.50905
Generation Dates on FileJun 2022 to Dec 2023
Initial Operation DateJune 2022
Annual Generation 10.3 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number17-341; 17-341-001
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityPuget Sound Energy (PSEI)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerPuget Sound Energy Inc (15500) WA
Grid Voltage 12.00 kV
Energy StorageNo

Generator CAMAS Details Operating June 2022

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity5 MW
Summer Capacity5 MW
Winter Capacity5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2022
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solar Details
Single Axis TrackingYes
Azimuth Angle180
Tilt Angle60
DC Net Capacity6.7 MW
Crystalline SiliconYes
Net Metering AgreementNo
Virtual Net Metering AgreementNo

Camas Solar Project Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#1495West PembertonPemberton Twp, NJ10.4 GWh
#1496Windsor Hwy 17 SolarWindsor, NC10.4 GWh
#1497Lane II Solar, LLCGoldsboro, NC10.4 GWh
#1498Penstemon Solar ProjectEllensburg, WA10.4 GWh
#1499Omtanke SolarRidgeville, SC10.4 GWh
#1500Harrison Solar, LLCRoseboro, NC10.4 GWh
#1501BRE NC Solar 3Oxford, NC10.3 GWh
#1502MCRD Parris Island PV HybridParris Island, SC31.5 GWh
#1503SunE CPS3 LLCSomerset, TX10.3 GWh
#1504OCI Alamo 3 LLCSan Antonio, TX10.3 GWh
#1506SR Greenville ILimestone, TN10.3 GWh
#1507Organ Church SolarRockwell, NC10.3 GWh
#1508Kalaeloa Solar TwoHonolulu, HI10.3 GWh
#1509Bailey Farm LLCBailey, NC10.3 GWh
#1510BadgerMaysville, NC10.3 GWh
#1511Marlin SolarMarlin, TX10.3 GWh
#1512Pilot Mountain Solar, LLCKing, NC10.2 GWh
#1513Whitesboro SolarWhitesboro, TX10.2 GWh
#1514Whitesboro Solar IIWhitesboro, TX10.2 GWh
#1515Hardison Farm Solar, LLCWilliamston, NC10.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Camas Solar Project.

Plant NamePlant LocationAnnual GenerationDistance
CowicheTieton, WA3.4 GWh21.4 mi
Crystal MountainGreenwater, WA200.0 MWh45.6 mi
Orchard Avenue 1Yakima, WA2.6 GWh26.3 mi
PackwoodPackwood, WA60.4 GWh56.1 mi
PEC HeadworksMoses Lake, WA18.7 GWh32 mi
Penstemon Solar ProjectEllensburg, WA10.4 GWh0 mi
Priest RapidsMattawa, WA3.8 TWh35.8 mi
Quincy ChuteQuincy, WA33.8 GWh59 mi
Rock IslandWenatchee, WA2.0 TWh33.1 mi
Rocky ReachWenatchee, WA4.8 TWh40.9 mi
RozaYakima, WA54.5 GWh23.6 mi
Sagebrush Power PartnersEllensburg, WA255.0 GWh14.8 mi
Swauk Wind LLCThorp, WA6.0 GWh16.9 mi
Tieton Dam Hydro Electric ProjectRimrock, WA45.0 GWh35.9 mi
Twin Falls HydroNorth Bend, WA50.0 GWh64.7 mi
Urtica Solar ProjectEllensburg, WA11.4 GWh13.3 mi
Vantage Wind Energy LLCEllensburg, WA231.6 GWh15.4 mi
WanapumBeverly, WA4.0 TWh26.1 mi
Weeks FallsNorth Bend, WA8.8 GWh62.7 mi
Wild HorseEllensburg, WA589.0 GWh15.2 mi