Bridgewater Power LP
Route #3, Bridgewater, NH 3217Plant Summary Information
Bridgewater Power LP is ranked #12 out of 56 power plants in New Hampshire in terms of total annual net electricity generation.
Bridgewater Power LP is comprised of 1 generator and generated 26.6 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Bridgewater Power LP |
---|---|
Utility Name | Bridgewater Power Co LP |
Location | Grafton County, NH |
Initial Operation Date | August 1987 |
Last Update | Dec 2023 |
Annual Generation | 109.2 GWh |
Annual Consumption | 1.9 M MMBtu |
Ranked #3,075 out of 11,835 Power Plants Nationwide | |
Ranked #64 out of 169 Wood/Wood Waste Solids Power Plants Nationwide | |
Ranked #12 out of 56 New Hampshire Power Plants | |
Ranked #2 out of 4 New Hampshire Wood/Wood Waste Solids Power Plants | |
Fuel Types | Wood/Wood Waste Solids : 99.8% |
Map of Bridgewater Power LP
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Bridgewater Power LP.
Monthly Net Generation for Bridgewater Power LP
Bridgewater Power LP Details
Summary Information | |
---|---|
Plant Name | Bridgewater Power LP (10290) |
Plant Address | Route #3, Bridgewater, NH 3217 |
Utility | Bridgewater Power Co LP (2226) |
Latitude, Longitude | 43.7155, -71.6585 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | August 1987 |
Annual Generation | 109.2 GWh |
Fuel Types | Wood/Wood Waste Solids : 99.8% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 86-53-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | ISO New England Inc. (ISNE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | Public Service Co of NH (15472) NH |
Grid Voltage | 36.00 kV |
Energy Storage | No |
Generator GEN1 Details Operating August 1987
Technology | Wood/Wood Waste Biomass |
---|---|
Prime Mover | Steam Turbine |
Ownership | Jointly Owned |
Nameplate Capacity | 20 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 16 MW |
Winter Capacity | 16.5 MW |
Minimum Load | 2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 1987 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
---|---|
Energy Source | Wood/Wood Waste Solids / Distillate Fuel Oil |
Startup Source | Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Fluidized Bed Technology | No |
Pulverized Coal Technology | No |
Stoker Technology | No |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Bridgewater Power LP Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Bridgewater Power Co LP | P O Box 678Route 3, Ashland, NH 3217 | 20.00% |
Olympus Power | 67 Park Place East, Morristown, NJ 7960 | 80.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wood/Wood Waste Solids.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#54 | Allendale Biomass | Fairfax, SC | 121.0 GWh |
#55 | Mansfield Mill | Mansfield, LA | 844.8 GWh |
#56 | DeRidder Mill | DeRidder, LA | 389.0 GWh |
#57 | St Paul Cogeneration | St. Paul, MN | 153.1 GWh |
#58 | National Energy of McBain | McBain, MI | 136.0 GWh |
#59 | National Energy of Lincoln | Lincoln, MI | 141.5 GWh |
#60 | Dillard Complex | Dillard, OR | 114.0 GWh |
#61 | International Paper Prattville Mill | Prattville, AL | 608.4 GWh |
#62 | John H Warden | L'Anse, MI | 125.5 GWh |
#63 | Genesee Power Station LP | Flint, MI | 114.8 GWh |
#65 | Sierra Pacific Aberdeen | Aberdeen, WA | 105.2 GWh |
#66 | Fernandina Beach Mill | Fernandina Beach, FL | 562.0 GWh |
#67 | International Paper Pensacola | Cantonment, FL | 336.2 GWh |
#68 | International Paper Georgetown Mill | Georgetown, SC | 495.9 GWh |
#69 | Kentucky Mills | Hawesville, KY | 327.9 GWh |
#70 | WestRock (TX) | Evadale, TX | 406.8 GWh |
#71 | PCA-Valdosta Mill | Valdosta, GA | 306.6 GWh |
#72 | Escanaba Mill | Escanaba, MI | 411.8 GWh |
#73 | International Paper - Orange | Orange, TX | 238.6 GWh |
#74 | Sierra Pacific Burney Facility | Burney, CA | 94.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Bridgewater Power LP.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Ayers Island | Bristol, NH | 54.4 GWh | 8.7 mi |
Clement Dam Hydro LLC | Tilton, NH | 11.9 GWh | 19.3 mi |
Dartmouth College Heating Plant | Hanover, NH | 10.0 GWh | 31.4 mi |
Eastman Falls | Franklin, NH | 33.2 GWh | 18.5 mi |
EHC West Hopkinton | West Hopkinton, NH | 4.0 GWh | 36.6 mi |
Elizabeth Mines Solar 1 | So. Strafford, VT | 6.9 GWh | 34.4 mi |
Groton Wind LLC | Groton, NH | 97.2 GWh | 8.8 mi |
Lochmere Hydroelectric Plant | Tilton, NH | 4.3 GWh | 17.9 mi |
Mascoma Hydro | W. Lebanon, NH | 3.5 GWh | 33.4 mi |
NE Renewable Springfield, LLC | Springfield, NH | 32.0 GWh | 27.4 mi |
Newfound Hydroelectric | Bristol, NH | 8.1 GWh | 9.4 mi |
Ottauquechee Hydro | N. Hartland, VT | 3.5 GWh | 35.6 mi |
Penacook Lower Falls | Boscawen, NH | 22.6 GWh | 29.9 mi |
Penacook Upper Falls Hydro | Penacook, NH | 17.1 GWh | 30 mi |
Rolfe Canal Hydro | Penacook, NH | 27.8 GWh | 30.6 mi |
Smith (VT) | Bradford, VT | 4.0 GWh | 30.2 mi |
Stevens Mills Dam | Franklin, NH | 9.8 GWh | 18.6 mi |
Wheelabrator Concord Facility | Concord, NH | 93.6 GWh | 29.9 mi |
White Lake | Tamworth, NH | 552.0 MWh | 24.3 mi |
Wilder | Hartford, VT | 192.4 GWh | 32.4 mi |