Boring Solar LLC
SE Dunn Road, Sandy, OR 97055Plant Summary Information
Boring Solar LLC is ranked #81 out of 114 solar farms in Oregon in terms of total annual net electricity generation.
Boring Solar LLC generated 534.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Boring Solar LLC |
---|---|
Utility Name | Boring Solar LLC |
Location | Clackamas County, OR |
Initial Operation Date | April 2019 |
Last Update | Dec 2023 |
Annual Generation | 3.8 GWh |
Annual Consumption | 13.3 k MMBtu |
Ranked #8,316 out of 11,852 Power Plants Nationwide | |
Ranked #3,273 out of 5,655 Solar Power Plants Nationwide | |
Ranked #213 out of 255 Oregon Power Plants | |
Ranked #81 out of 114 Oregon Solar Power Plants | |
Fuel Types | Solar |
Map of Boring Solar LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Boring Solar LLC.
Monthly Net Generation for Boring Solar LLC
Boring Solar LLC Details
Summary Information | |
---|---|
Plant Name | Boring Solar LLC (62169) |
Plant Address | SE Dunn Road, Sandy, OR 97055 |
Utility | Boring Solar LLC (61705) |
Latitude, Longitude | 45.431, -122.285 |
Generation Dates on File | Apr 2019 to Dec 2023 |
Initial Operation Date | April 2019 |
Annual Generation | 3.8 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | 16-274-000, 16-274-001 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Portland General Electric Company (PGE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Portland General Electric Co (15248) OR |
Grid Voltage | 12.47 kV |
Energy Storage | No |
Generator BSPV2 Details Operating April 2019
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 2.2 MW |
Summer Capacity | 2.2 MW |
Winter Capacity | 2.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2019 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Fixed Tilt | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 20 |
DC Net Capacity | 3.4 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Boring Solar LLC Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3263 | Black Cap Solar Plant | Lakeview, OR | 3.8 GWh |
#3264 | Fresno Solar | San Joaquin, CA | 3.8 GWh |
#3265 | Route 76 Boone Solar 1 | Poplar Grove, IL | 3.8 GWh |
#3266 | Rafael Solar | Salem, OR | 3.8 GWh |
#3267 | Briscoe 2A | Lostant, IL | 3.8 GWh |
#3268 | Pivot Solar 3 LLC (CSG) | Parachute, CO | 3.8 GWh |
#3269 | Comer Solar | Comer, GA | 3.8 GWh |
#3270 | Wonderful Huller & Shellling | Lost Hills, CA | 3.8 GWh |
#3271 | NHA at Mansfield NJ | Washington, NJ | 3.8 GWh |
#3272 | Exeter Solar | Exeter, CA | 3.8 GWh |
#3274 | SCCCD - Fresno Community College | Fresno, CA | 3.8 GWh |
#3275 | Hendershot Solar, LLC | Tecumseh, MI | 3.8 GWh |
#3276 | Pivot Solar 2 LLC (CSG) | Brush, CO | 3.8 GWh |
#3277 | Fountain | Fountain, MN | 3.8 GWh |
#3278 | Lowe Solar Energy Storage | Asheboro, NC | 3.7 GWh |
#3279 | Day Hill Solar, LLC | Estacada, OR | 3.8 GWh |
#3280 | Spencer Meadow Solar Energy Storage | Asheboro, NC | 3.7 GWh |
#3281 | City of Bowie | Mitchellville, MD | 3.8 GWh |
#3282 | Franklin Solar 2 | Louisburg, NC | 3.8 GWh |
#3283 | SCE-Snowline-White Rd (Central) | Phelan, CA | 3.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Boring Solar LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bonneville | Cascade Locks, OR | 3.5 TWh | 22.2 mi |
Brightwood Solar, LLC | Sandy, OR | 15.8 GWh | 10.2 mi |
Colton Solar | Molalla, OR | 3.5 GWh | 20.2 mi |
Day Hill Solar, LLC | Estacada, OR | 3.8 GWh | 11.4 mi |
Dunn Road Solar | Sandy, OR | 3.1 GWh | 0 mi |
Duus Solar, LLC | Estacada, OR | 19.2 GWh | 8.1 mi |
Faraday | Estacada, OR | 92.5 GWh | 11.4 mi |
Firwood Solar, LLC | Sandy, OR | 19.6 GWh | 5.8 mi |
North Fork | Estacada, OR | 155.1 GWh | 13 mi |
NSE Astoria - Skyward | Boring, OR | 3.8 GWh | 0.9 mi |
Oregon Convention Center | Portland, OR | 1.7 GWh | 19.5 mi |
PHP 1 | Sandy, OR | 40.2 GWh | 10.4 mi |
PHP 2 | Sandy, OR | 30.2 GWh | 6.6 mi |
River Mill | Estacada, OR | 83.8 GWh | 9.6 mi |
Sandy River Solar (CSG) | Sandy, OR | 2.9 GWh | 0.5 mi |
SSD Clackamas 1, LLC | Boring, OR | 6.5 GWh | 2.4 mi |
Sullivan | West Linn, OR | 93.4 GWh | 17.1 mi |
SulusSolar17 | Oregon City, OR | 4.2 GWh | 9.2 mi |
SulusSolar29 | Boring, OR | 3.8 GWh | 2 mi |
Tickle Creek Solar | Sandy, OR | 3.1 GWh | 4 mi |