Blythe Solar III, LLC Hybrid
4000 Dracker Drive, Blythe, CA 92225Plant Summary Information
Blythe Solar III, LLC Hybrid is ranked #40 out of 799 solar farms in California in terms of total annual net electricity generation.
Blythe Solar III, LLC Hybrid generated 105.7 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Blythe Solar III, LLC Hybrid |
---|---|
Utility Name | Blythe Solar III, LLC |
Location | Riverside County, CA |
Initial Operation Date | May 2020 |
Last Update | Sep 2024 |
Annual Generation | 346.5 GWh |
Annual Consumption | 1.3 M MMBtu |
Ranked #1,667 out of 11,852 Power Plants Nationwide | |
Ranked #118 out of 5,655 Solar Power Plants Nationwide | |
Ranked #134 out of 1,570 California Power Plants | |
Ranked #40 out of 799 California Solar Power Plants | |
Fuel Types | Solar |
Map of Blythe Solar III, LLC Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blythe Solar III, LLC Hybrid.
Monthly Net Generation for Blythe Solar III, LLC Hybrid
Blythe Solar III, LLC Hybrid Details
Summary Information | |
---|---|
Plant Name | Blythe Solar III, LLC Hybrid (60094) |
Plant Address | 4000 Dracker Drive, Blythe, CA 92225 |
Utility | Blythe Solar III, LLC (59844) |
Latitude, Longitude | 33.656, -114.742 |
Generation Dates on File | May 2020 to Sep 2024 |
Initial Operation Date | May 2020 |
Annual Generation | 346.5 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | Yes |
Generator BLSL3 Details Operating May 2020
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 136.8 MW |
Summer Capacity | 136.8 MW |
Winter Capacity | 136.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 154 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLST3 Details Operating May 2021
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 115 MW |
Summer Capacity | 115 MW |
Winter Capacity | 115 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 538.6 |
---|---|
Maximum Charge Rate | 115 MW |
Maximum Discharge Rate | 115 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 126.9 |
Storage Enclosure Type | CS |
Arbitrage | Yes |
Frequency Regulation | P |
Ramping Spinning Reserve | Yes |
Load Management | Yes |
Voltage Or Reactive Power Support | Yes |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Blythe Solar III, LLC Hybrid Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#108 | Solar Gen 2 Solar Facility | Calipatria, CA | 376.5 GWh |
#109 | Brazoria County Solar Project (Danciger) | Damon, TX | 376.3 GWh |
#110 | Texas Solar Nova 2 | Spur, TX | 375.9 GWh |
#111 | Maverick Solar, LLC | Desert Center, CA | 375.9 GWh |
#112 | Buckthorn Westex | Ft. Stockton, TX | 375.1 GWh |
#113 | Indiana Crossroads Solar Park | Reynolds, IN | 366.8 GWh |
#114 | Prairie Wolf Solar LLC | Ashmore Township, IL | 366.4 GWh |
#115 | RE Roserock | Fort Stockton, TX | 363.0 GWh |
#116 | Horizon Solar | Pearsall, TX | 361.5 GWh |
#117 | Fifth Standard Solar PV, LLC (Hybrid) | Huron, CA | 337.8 GWh |
#119 | Wright Solar Park | Los Banos, CA | 354.7 GWh |
#120 | Impact Solar 1 | Deport, TX | 353.3 GWh |
#121 | Victory Pass | Desert Center, CA | 352.9 GWh |
#122 | Calhoun Solar | Battle Creek, MI | 352.3 GWh |
#123 | Oak Ridge Solar | Oak Ridge, LA | 352.2 GWh |
#124 | Aragorn Solar Project | Van Horn, TX | 350.4 GWh |
#125 | Edwards Sanborn E1B | Mojave, CA | 333.6 GWh |
#126 | Skipjack Solar Center | Wayside, VA | 349.3 GWh |
#127 | Camilla Solar Energy Project | Camilla, GA | 349.2 GWh |
#128 | Pike Solar Hybrid | Fountain, CO | 349.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blythe Solar III, LLC Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arica Solar | Desert Center, CA | 461.5 GWh | 33.2 mi |
Arlington Energy Center II | Blythe, CA | 628.1 GWh | 3.1 mi |
Arlington Energy Center III | Blythe, CA | 266.5 GWh | 3.1 mi |
Blythe Energy Inc | Blythe, CA | 1.0 TWh | 4.2 mi |
Blythe Mesa Solar II | Blythe, CA | 544.2 GWh | 3.7 mi |
Blythe Solar 110, LLC | Blythe, CA | 584.2 GWh | 1.7 mi |
Blythe Solar II, LLC | Blythe, CA | 331.9 GWh | 1.8 mi |
Blythe Solar IV, LLC | Blythe, CA | 302.6 GWh | 2.3 mi |
Chuckawalla Solar | Blythe, CA | 6.8 GWh | 11.8 mi |
Chuckawalla Valley State Prison | Blythe, CA | 1.2 GWh | 11.2 mi |
Genesis Solar Energy Project | Blythe, CA | 613.8 GWh | 14.7 mi |
Ironwood Solar LLC | Blythe, CA | 8.2 GWh | 11.9 mi |
McCoy Solar Energy Project Hybrid | Blythe, CA | 524.7 GWh | 2.7 mi |
Palo Verde College | Blythe, CA | 2.0 GWh | 5.2 mi |
Solar Blythe 2 | Blythe, CA | 40.5 GWh | 3.7 mi |
Solar Blythe LLC | Blythe, CA | 40.5 GWh | 4.4 mi |
SunEdison Ironwood State Prison | Blythe, CA | 1.3 GWh | 11.8 mi |
Venable Solar 1 | Blythe, CA | 3.4 GWh | 10.6 mi |
Venable Solar 2 | Blythe, CA | 3.4 GWh | 10.6 mi |
Victory Pass | Desert Center, CA | 352.9 GWh | 33.2 mi |