Blythe Solar II, LLC
4000 Dracker Drive, Blythe, CA 92225Plant Summary Information
Blythe Solar II, LLC is ranked #46 out of 806 solar farms in California in terms of total annual net electricity generation.
Blythe Solar II, LLC generated 63.3 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Blythe Solar II, LLC |
---|---|
Utility Name | Blythe Solar II, LLC |
Location | Riverside County, CA |
Initial Operation Date | July 2016 |
Last Update | Dec 2024 |
Annual Generation | 334.1 GWh |
Annual Consumption | 1.2 M MMBtu |
Ranked #1,746 out of 11,949 Power Plants Nationwide | |
Ranked #143 out of 5,739 Solar Power Plants Nationwide | |
Ranked #150 out of 1,577 California Power Plants | |
Ranked #46 out of 806 California Solar Power Plants | |
Fuel Types | Solar |
Map of Blythe Solar II, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blythe Solar II, LLC.
Monthly Net Generation for Blythe Solar II, LLC
Blythe Solar II, LLC Details
Summary Information | |
---|---|
Plant Name | Blythe Solar II, LLC (60092) |
Plant Address | 4000 Dracker Drive, Blythe, CA 92225 |
Utility | Blythe Solar II, LLC (59843) |
Latitude, Longitude | 33.68, -114.73 |
Generation Dates on File | Jul 2016 to Dec 2024 |
Initial Operation Date | July 2016 |
Annual Generation | 334.1 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | Yes |
Generator BLCK7 Details Operating October 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 32.1 MW |
Summer Capacity | 32.1 MW |
Winter Capacity | 32.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 39.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK4 Details Operating July 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 33.2 MW |
Summer Capacity | 33.2 MW |
Winter Capacity | 33.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 41 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK5 Details Operating August 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 33.9 MW |
Summer Capacity | 33.9 MW |
Winter Capacity | 33.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 41.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK6 Details Operating September 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 32 MW |
Summer Capacity | 32 MW |
Winter Capacity | 32 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 39.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLST2 Details Operating March 2021
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 115 MW |
Summer Capacity | 115 MW |
Winter Capacity | 115 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 538.6 |
---|---|
Maximum Charge Rate | 115 MW |
Maximum Discharge Rate | 115 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 126.9 |
Storage Enclosure Type | CS |
Arbitrage | Yes |
Frequency Regulation | P |
Ramping Spinning Reserve | Yes |
Load Management | Yes |
Voltage Or Reactive Power Support | Yes |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Blythe Solar II, LLC Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#133 | Lund Hill Solar | Bickleton, WA | 353.6 GWh |
#134 | Hecate Energy Highland LLC | Buford, OH | 349.9 GWh |
#135 | Copper Mountain Solar 2 | Boulder City, NV | 348.7 GWh |
#136 | Arlington Valley Solar Energy II | Arlington, AZ | 348.5 GWh |
#137 | Imperial Valley Solar, LLC | Calexico, CA | 346.4 GWh |
#138 | Hopkins Energy LLC | Dike, TX | 346.2 GWh |
#139 | Aragorn Solar Project | Van Horn, TX | 344.3 GWh |
#140 | Fifth Standard Solar PV, LLC (Hybrid) | Huron, CA | 321.3 GWh |
#141 | Skipjack Solar Center | Wayside, VA | 343.4 GWh |
#142 | Edwards Sanborn E1A | Mojave, CA | 327.2 GWh |
#144 | Impact Solar 1 | Deport, TX | 339.7 GWh |
#145 | Wright Solar Park | Los Banos, CA | 337.9 GWh |
#146 | Newport Solar Project | Newport, AR | 337.4 GWh |
#147 | BigBeau Solar, LLC | Rosamond, CA | 330.0 GWh |
#148 | Ganado Solar | Gail, TX | 325.8 GWh |
#149 | Quitman Solar | Quitman, GA | 330.5 GWh |
#150 | Big River Solar | Norris City, IL | 329.9 GWh |
#151 | Campo Verde Solar | El Centro, CA | 328.6 GWh |
#152 | CA Flats Solar 150, LLC | Shandon, CA | 325.6 GWh |
#153 | American Kings Solar, LLC | Lemoore, CA | 323.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blythe Solar II, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arica Solar | Desert Center, CA | 552.5 GWh | 33.7 mi |
Arlington Energy Center II | Blythe, CA | 635.6 GWh | 2.7 mi |
Arlington Energy Center III | Blythe, CA | 273.9 GWh | 2.7 mi |
Blythe Energy Inc | Blythe, CA | 645.1 GWh | 5.1 mi |
Blythe Mesa Solar II | Blythe, CA | 552.0 GWh | 3.9 mi |
Blythe Solar 110, LLC | Blythe, CA | 584.2 GWh | 0.7 mi |
Blythe Solar III, LLC Hybrid | Blythe, CA | 349.4 GWh | 1.8 mi |
Blythe Solar IV, LLC | Blythe, CA | 298.8 GWh | 2.2 mi |
Chuckawalla Solar | Blythe, CA | 6.8 GWh | 13.3 mi |
Chuckawalla Valley State Prison | Blythe, CA | 1.2 GWh | 12.7 mi |
Desert Quartzite | Blythe, CA | 81.7 GWh | 8.1 mi |
Genesis Solar Energy Project | Blythe, CA | 623.7 GWh | 15.4 mi |
Ironwood Solar LLC | Blythe, CA | 8.2 GWh | 13.4 mi |
McCoy Solar Energy Project Hybrid | Blythe, CA | 524.7 GWh | 1.2 mi |
Palo Verde College | Blythe, CA | 2.0 GWh | 4.7 mi |
Solar Blythe 2 | Blythe, CA | 40.5 GWh | 4.7 mi |
Solar Blythe LLC | Blythe, CA | 40.5 GWh | 6.2 mi |
SunEdison Ironwood State Prison | Blythe, CA | 1.3 GWh | 13.3 mi |
Venable Solar 1 | Blythe, CA | 3.4 GWh | 10.7 mi |
Venable Solar 2 | Blythe, CA | 3.4 GWh | 10.8 mi |