Blythe Solar II, LLC
4000 Dracker Drive, Blythe, CA 92225Plant Summary Information
Blythe Solar II, LLC is ranked #46 out of 799 solar farms in California in terms of total annual net electricity generation.
Blythe Solar II, LLC generated 95.0 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Blythe Solar II, LLC |
---|---|
Utility Name | Blythe Solar II, LLC |
Location | Riverside County, CA |
Initial Operation Date | July 2016 |
Last Update | Sep 2024 |
Annual Generation | 331.9 GWh |
Annual Consumption | 1.3 M MMBtu |
Ranked #1,727 out of 11,852 Power Plants Nationwide | |
Ranked #136 out of 5,655 Solar Power Plants Nationwide | |
Ranked #150 out of 1,570 California Power Plants | |
Ranked #46 out of 799 California Solar Power Plants | |
Fuel Types | Solar |
Map of Blythe Solar II, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blythe Solar II, LLC.
Monthly Net Generation for Blythe Solar II, LLC
Blythe Solar II, LLC Details
Summary Information | |
---|---|
Plant Name | Blythe Solar II, LLC (60092) |
Plant Address | 4000 Dracker Drive, Blythe, CA 92225 |
Utility | Blythe Solar II, LLC (59843) |
Latitude, Longitude | 33.68, -114.73 |
Generation Dates on File | Jul 2016 to Sep 2024 |
Initial Operation Date | July 2016 |
Annual Generation | 331.9 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | Yes |
Generator BLCK7 Details Operating October 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 32.1 MW |
Summer Capacity | 32.1 MW |
Winter Capacity | 32.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 39.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK4 Details Operating July 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 33.2 MW |
Summer Capacity | 33.2 MW |
Winter Capacity | 33.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | July 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 41 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK5 Details Operating August 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 33.9 MW |
Summer Capacity | 33.9 MW |
Winter Capacity | 33.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | August 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 41.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLCK6 Details Operating September 2016
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 32 MW |
Summer Capacity | 32 MW |
Winter Capacity | 32 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2016 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 39.5 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator BLST2 Details Operating March 2021
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 115 MW |
Summer Capacity | 115 MW |
Winter Capacity | 115 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2021 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 538.6 |
---|---|
Maximum Charge Rate | 115 MW |
Maximum Discharge Rate | 115 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 126.9 |
Storage Enclosure Type | CS |
Arbitrage | Yes |
Frequency Regulation | P |
Ramping Spinning Reserve | Yes |
Load Management | Yes |
Voltage Or Reactive Power Support | Yes |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Blythe Solar II, LLC Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#126 | Skipjack Solar Center | Wayside, VA | 349.3 GWh |
#127 | Camilla Solar Energy Project | Camilla, GA | 349.2 GWh |
#128 | Pike Solar Hybrid | Fountain, CO | 349.1 GWh |
#129 | Lund Hill Solar | Bickleton, WA | 349.0 GWh |
#130 | Copper Mountain Solar 2 | Boulder City, NV | 348.7 GWh |
#131 | Arlington Valley Solar Energy II | Arlington, AZ | 348.5 GWh |
#132 | Bernard Creek Solar | Hungerford, TX | 347.8 GWh |
#133 | Imperial Valley Solar, LLC | Calexico, CA | 346.4 GWh |
#134 | Big Cypress Solar, LLC | Crawfordsville, AR | 342.9 GWh |
#135 | Edwards Sanborn E1A | Mojave, CA | 325.8 GWh |
#137 | Big River Solar | Norris City, IL | 334.0 GWh |
#138 | Quitman Solar | Quitman, GA | 330.2 GWh |
#139 | Campo Verde Solar | El Centro, CA | 328.6 GWh |
#140 | Newport Solar Project | Newport, AR | 328.2 GWh |
#141 | CA Flats Solar 150, LLC | Shandon, CA | 327.6 GWh |
#142 | Sparta Solar | Pawnee, TX | 325.6 GWh |
#143 | American Kings Solar, LLC | Lemoore, CA | 325.3 GWh |
#144 | Umbriel Solar | Livington, TX | 320.8 GWh |
#145 | Ganado Solar | Gail, TX | 316.8 GWh |
#146 | Tres Bahias | Port Lavaca, TX | 319.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blythe Solar II, LLC.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arica Solar | Desert Center, CA | 461.5 GWh | 33.7 mi |
Arlington Energy Center II | Blythe, CA | 628.1 GWh | 2.7 mi |
Arlington Energy Center III | Blythe, CA | 266.5 GWh | 2.7 mi |
Blythe Energy Inc | Blythe, CA | 1.0 TWh | 5.1 mi |
Blythe Mesa Solar II | Blythe, CA | 544.2 GWh | 3.9 mi |
Blythe Solar 110, LLC | Blythe, CA | 584.2 GWh | 0.7 mi |
Blythe Solar III, LLC Hybrid | Blythe, CA | 346.5 GWh | 1.8 mi |
Blythe Solar IV, LLC | Blythe, CA | 302.6 GWh | 2.2 mi |
Chuckawalla Solar | Blythe, CA | 6.8 GWh | 13.3 mi |
Chuckawalla Valley State Prison | Blythe, CA | 1.2 GWh | 12.7 mi |
Genesis Solar Energy Project | Blythe, CA | 613.8 GWh | 15.4 mi |
Ironwood Solar LLC | Blythe, CA | 8.2 GWh | 13.4 mi |
McCoy Solar Energy Project Hybrid | Blythe, CA | 524.7 GWh | 1.2 mi |
Palo Verde College | Blythe, CA | 2.0 GWh | 4.7 mi |
Solar Blythe 2 | Blythe, CA | 40.5 GWh | 4.7 mi |
Solar Blythe LLC | Blythe, CA | 40.5 GWh | 6.2 mi |
SunEdison Ironwood State Prison | Blythe, CA | 1.3 GWh | 13.3 mi |
Venable Solar 1 | Blythe, CA | 3.4 GWh | 10.7 mi |
Venable Solar 2 | Blythe, CA | 3.4 GWh | 10.8 mi |
Victory Pass | Desert Center, CA | 352.9 GWh | 33.7 mi |