Barney M Davis
4301 Waldron Rd, Corpus Christi, TX 78418Plant Summary Information
Barney M Davis is ranked #63 out of 304 natural gas power plants in Texas in terms of total annual net electricity generation.
Barney M Davis is comprised of 4 generators and generated 335.3 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Barney M Davis |
---|---|
Utility Name | Talen Texas, LLC |
Location | Nueces County, TX |
Initial Operation Date | May 1974 |
Last Update | Dec 2024 |
Annual Generation | 1.6 TWh |
Annual Consumption | 13.0 M MMBtu |
Ranked #581 out of 11,949 Power Plants Nationwide | |
Ranked #365 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #84 out of 769 Texas Power Plants | |
Ranked #63 out of 304 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operators |
Topaz Power Group LLC (2013 to 2015) Topaz Power Group LLC (2016 to 2016) Topaz Power Group GP II, LLC (2017 to 2018) Talen Texas, LLC (2019 to 2023) |
Map of Barney M Davis
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Barney M Davis.
Monthly Net Generation for Barney M Davis
Barney M Davis Details
Summary Information | |
---|---|
Plant Name | Barney M Davis (4939) |
Plant Address | 4301 Waldron Rd, Corpus Christi, TX 78418 |
Utility | Talen Texas, LLC (49979) |
Latitude, Longitude | 27.6064, -97.3117 |
Generation Dates on File | Jan 2001 to Dec 2024 |
Initial Operation Date | May 1974 |
Annual Generation | 1.6 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 04-62-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Laguna Madre |
Ash Impoundment | No |
Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | TEXAS EASTERN TRANSMISSION LP |
Natural Gas Storage | No |
Generator 1 Details Operating May 1974
Technology | Natural Gas Steam Turbine |
---|---|
Prime Mover | Steam Turbine |
Ownership | Single Owner |
Nameplate Capacity | 352 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 292 MW |
Winter Capacity | 292 MW |
Minimum Load | 60 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 1974 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | OVER |
Multiple Fuels | No |
Generator 2 Details Operating July 1976
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 351 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 319 MW |
Winter Capacity | 325 MW |
Minimum Load | 100 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | July 1976 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator 3 Details Operating March 2010
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 189.6 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 157 MW |
Winter Capacity | 165 MW |
Minimum Load | 60 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2010 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator 4 Details Operating March 2010
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 189.6 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 157 MW |
Winter Capacity | 165 MW |
Minimum Load | 60 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2010 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Barney M Davis Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#355 | Effingham Energy Facility | Rincon, GA | 1.7 TWh |
#356 | Anclote | Holiday, FL | 1.6 TWh |
#357 | James E. Rogers Energy Complex | Cliffside, NC | 4.4 TWh |
#358 | Shell Chemical Appalachia LLC | Monaca, PA | 1.6 TWh |
#359 | Sutter Energy Center | Yuba City, CA | 1.6 TWh |
#360 | Pueblo Airport Generating Station | Pueblo, CO | 1.6 TWh |
#361 | Theodore Cogen Facility | Theodore, AL | 1.6 TWh |
#362 | Kendall Square Station | Cambridge, MA | 1.6 TWh |
#363 | Trimble County | Bedford, KY | 9.1 TWh |
#364 | River Road Gen Plant | Vancouver, WA | 1.6 TWh |
#366 | Magnolia Power Project | Burbank, CA | 1.6 TWh |
#367 | Emporia Energy Center | Emporia, KS | 1.5 TWh |
#368 | LaO Energy Systems | Plaquemine, LA | 1.8 TWh |
#369 | PPG Powerhouse C | Lake Charles, LA | 1.5 TWh |
#370 | Walnut Energy Center | Turlock, CA | 1.5 TWh |
#371 | Valley (CA) | Sun Valley, CA | 1.5 TWh |
#372 | Pioneer Generation Station | Williston, ND | 1.5 TWh |
#373 | Tenaska Gateway Generating Station | Mt. Enterprise, TX | 1.5 TWh |
#374 | Westlake Plaquemine | Plaquemine, LA | 1.5 TWh |
#375 | Motiva Enterprises Port Arthur Refinery | Port Arthur, TX | 1.7 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Barney M Davis.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Baffin Wind | Sarita, TX | 323.5 GWh | 34 mi |
Chapman Ranch Wind I | Corpus Christi, TX | 595.2 GWh | 11.6 mi |
Corpus Christi | Corpus Christi, TX | 72.9 GWh | 22.4 mi |
Corpus Christi Energy Center | Corpus Christi, TX | 2.5 TWh | 16 mi |
Corpus Refinery | Corpus Christi, TX | 272.8 GWh | 20.5 mi |
El Algodon Alto Wind Farm, LLC | Mathis, TX | 623.3 GWh | 37.6 mi |
Gregory Power Plant | Gregory, TX | 841.1 GWh | 19.8 mi |
HEB00057 | Corpus Christi, TX | 315.0 MWh | 4.5 mi |
HEB00069 | Corpus Christi, TX | 407.0 MWh | 6.8 mi |
HEBCCBakery | Corpus Christi, TX | 1.0 GWh | 15.5 mi |
Ingleside Cogeneration | Houston, TX | 2.7 TWh | 19.6 mi |
Midway Wind, LLC | Taft, TX | 398.0 GWh | 24.1 mi |
Nueces Bay | Corpus Christi, TX | 1.7 TWh | 16.1 mi |
Papalote Creek I LLC | Taft, TX | 421.0 GWh | 24.6 mi |
Papalote Creek II LLC | Taft, TX | 441.9 GWh | 26.9 mi |
Patriot Wind Farm | Bishop, TX | 570.9 GWh | 20.2 mi |
Peacock Energy Project | TX | 11.8 GWh | 27.6 mi |
Penascal II Wind Project LLC | Sarita, TX | 249.1 GWh | 36.7 mi |
Ticona Polymers Inc | Bishop, TX | 254.1 GWh | 31.4 mi |
Valero Refinery Corpus Christi West | Corpus Christi, TX | 99.3 GWh | 17.9 mi |