ATT North Watney
2525 North Watney Way, Fairfield, CA 94533Plant Summary Information
ATT North Watney is ranked #260 out of 346 natural gas power plants in California in terms of total annual net electricity generation.
ATT North Watney is comprised of 1 generator and generated 6.6 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | ATT North Watney |
---|---|
Utility Name | Bloom Energy |
Location | Solano County, CA |
Initial Operation Date | December 2019 |
Last Update | Dec 2023 |
Annual Generation | 6.6 GWh |
Annual Consumption | 50.5 k MMBtu |
Ranked #7,078 out of 11,852 Power Plants Nationwide | |
Ranked #1,685 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #989 out of 1,570 California Power Plants | |
Ranked #260 out of 346 California Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of ATT North Watney
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for ATT North Watney.
Monthly Net Generation for ATT North Watney
ATT North Watney Details
Summary Information | |
---|---|
Plant Name | ATT North Watney (63605) |
Plant Address | 2525 North Watney Way, Fairfield, CA 94533 |
Utility | Bloom Energy (57128) |
Latitude, Longitude | 38.23626, -122.07776 |
Generation Dates on File | Dec 2019 to Dec 2023 |
Initial Operation Date | December 2019 |
Annual Generation | 6.6 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Telecommunications (517) |
Sector | Commercial Non-CHP (4) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
Grid Voltage | 12.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | PACIFIC GAS |
Pipeline Name | PACIFIC GAS |
Natural Gas Storage | No |
Generator ATT35 Details Operating December 2019
Technology | Other Natural Gas |
---|---|
Prime Mover | Fuel Cell |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 2 MW |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2019 |
Combined Heat & Power | No |
Sector Name | Commercial Non-CHP (4) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
ATT North Watney Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Key Equipment Finance | 1000 McCaslin Blvd, Superior, CO 80027 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1675 | AT&T - Redwood City | Redwood City, CA | 7.0 GWh |
#1676 | Orrville | Orrville, OH | 20.8 GWh |
#1677 | Southern Minnesota Beet Sugar | Renville, MN | 25.6 GWh |
#1678 | Waste Management Eco Vista LFGTE | Springdale, AR | 6.9 GWh |
#1679 | Bos Dairy, LLC | Fair Oaks, IN | 6.8 GWh |
#1680 | CalTech - Pasadena | Pasadena, CA | 6.8 GWh |
#1681 | Georgia LFG Oak Grove Plant | Winder, GA | 38.4 GWh |
#1682 | HEBHoustonDistributionCenter | Houston, TX | 6.8 GWh |
#1683 | POET Biorefining - Chancellor | Chancellor, SD | 23.4 GWh |
#1684 | Combustion Turbine Project No 2 | Lodi, CA | 6.6 GWh |
#1686 | CBS Television City | Los Angeles, CA | 7.7 GWh |
#1687 | Maxim | San Jose, CA | 6.6 GWh |
#1688 | Xilinx San Jose | San Jose, CA | 6.5 GWh |
#1689 | AT&T - San Diego Trade Street | San Diego, CA | 6.5 GWh |
#1690 | San Diego Community College | San Diego, CA | 6.5 GWh |
#1691 | CBS Studio Center | Los Angeles, CA | 6.5 GWh |
#1692 | Foster Wheeler Mt Carmel Cogen | Marion Heights, PA | 103.7 GWh |
#1693 | Taylor Farms - Schilling Place | Salinas, CA | 6.5 GWh |
#1694 | South Oaks Hospital | Amityville, NY | 6.4 GWh |
#1695 | Indian River Plant | Titusville, FL | 6.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding ATT North Watney.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
American Canyon Solar | American Canyon, CA | 6.6 GWh | 9 mi |
Anheuser Busch - Fairfield | Fairfield, CA | 21.6 GWh | 0.8 mi |
Anheuser-Busch #2 | Fairfield, CA | 3.6 GWh | 0.8 mi |
CDCR (CA) - Solano State Prison | Vacaville, CA | 2.3 GWh | 8.3 mi |
Creed Energy Center | Suisun, CA | 8.2 GWh | 12.1 mi |
Foundation AB | Fairfield, CA | 2.9 GWh | 0.9 mi |
Genentech Vacaville Meter #1 | Vacaville, CA | 12.4 GWh | 12.8 mi |
Goose Haven Energy Center | Suisun, CA | 15.7 GWh | 12.7 mi |
Kaiser Napa Valley Corporate Dr Fuel Cell | Napa, CA | 37.4 GWh | 10.7 mi |
Lake Herman | Benicia, CA | 13.1 GWh | 10.2 mi |
Lambie Energy Center | Suisun, CA | 14.3 GWh | 11.4 mi |
Mariani Packing Vacaville Solar | Vacaville, CA | 891.0 MWh | 12.9 mi |
North Bay Solar 1 | Fairfield, CA | 1.6 GWh | 7.5 mi |
Potrero Hills Energy Producers | Suisun City, CA | 58.7 GWh | 5.5 mi |
SFDK Solar | Vallejo, CA | 10.0 GWh | 11 mi |
Solano County Cogen Plant | Fairfield, CA | 7.6 GWh | 2.3 mi |
Soscol Ferry Solar | Napa, CA | 4.3 GWh | 10.7 mi |
SunEdison Anheuser Busch Fairfield | Fairfield, CA | 747.0 MWh | 0.9 mi |
Valero Refinery Cogeneration Unit 1 | Benicia, CA | 181.8 GWh | 11.8 mi |
Wolfskill Energy Center | Fairfield, CA | 8.0 GWh | 0.6 mi |