Arvah B Hopkins
1125 Geddie Road, Tallahassee, FL 32304Plant Summary Information
Arvah B Hopkins is ranked #31 out of 279 power plants in Florida in terms of total annual net electricity generation.
Arvah B Hopkins is comprised of 9 generators and generated 482.9 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Arvah B Hopkins |
---|---|
Utility Name | City of Tallahassee - (FL) |
Location | Leon County, FL |
Initial Operation Date | February 1970 |
Last Update | Sep 2024 |
Annual Generation | 1.6 TWh |
Annual Consumption | 14.2 M MMBtu |
Ranked #561 out of 11,852 Power Plants Nationwide | |
Ranked #354 out of 2,254 Natural Gas Power Plants Nationwide | |
Ranked #31 out of 279 Florida Power Plants | |
Ranked #30 out of 85 Florida Natural Gas Power Plants | |
Fuel Types | Natural Gas : 99.9% |
Map of Arvah B Hopkins
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Arvah B Hopkins.
Monthly Net Generation for Arvah B Hopkins
Arvah B Hopkins Details
Summary Information | |
---|---|
Plant Name | Arvah B Hopkins (688) |
Plant Address | 1125 Geddie Road, Tallahassee, FL 32304 |
Utility | City of Tallahassee - (FL) (18445) |
Latitude, Longitude | 30.4522, -84.4 |
Generation Dates on File | Jan 2001 to Sep 2024 |
Initial Operation Date | February 1970 |
Annual Generation | 1.6 TWh |
Fuel Types | Natural Gas : 99.9% |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | SERC |
Balancing Authority | City of Tallahassee (TAL) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | City of Tallahassee - (FL) (18445) FL |
Grid Voltage | 230.00 kV / 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | FLORIDA GAS TRANSMISSION COMPANY |
Natural Gas Storage | No |
Generator 2 Details Operating October 1977
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC1 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 259.2 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 141 MW |
Winter Capacity | 145 MW |
Minimum Load | 120 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1977 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator GT4 Details Operating November 2005
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 46 MW |
Winter Capacity | 48 MW |
Minimum Load | 12 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | November 2005 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 42 MW |
Net Winter Capacity With Natural Gas | 48 MW |
Net Summer Capacity With Oil | 42 MW |
Net Winter Capacity With Oil | 48 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator GT3 Details Operating September 2005
Technology | Natural Gas Fired Combustion Turbine |
---|---|
Prime Mover | Combustion Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 60.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 46 MW |
Winter Capacity | 48 MW |
Minimum Load | 12 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 42 MW |
Net Winter Capacity With Natural Gas | 48 MW |
Net Summer Capacity With Oil | 42 MW |
Net Winter Capacity With Oil | 48 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator CT 2A Details Operating October 2008
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 198.9 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 159 MW |
Winter Capacity | 185 MW |
Minimum Load | 70 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | October 2008 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas / Distillate Fuel Oil |
Startup Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 159 MW |
Net Winter Capacity With Natural Gas | 175 MW |
Net Summer Capacity With Oil | 159 MW |
Net Winter Capacity With Oil | 175 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Air Permit Limits | Yes |
Generator IC1 Details Operating January 2019
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 18.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.5 MW |
Winter Capacity | 18.5 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2019 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator IC2 Details Operating January 2019
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 18.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.5 MW |
Winter Capacity | 18.5 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2019 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator IC3 Details Operating January 2019
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 18.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.5 MW |
Winter Capacity | 18.5 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2019 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator IC4 Details Operating January 2019
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 18.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.5 MW |
Winter Capacity | 18.5 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2019 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator IC5 Details Operating April 2020
Technology | Natural Gas Internal Combustion Engine |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | N/A |
RTO ISO Location Designation For Reporting Wholesale Sales Data | N/A |
Nameplate Capacity | 18.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 18.5 MW |
Winter Capacity | 18.5 MW |
Minimum Load | 7.5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2020 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Arvah B Hopkins Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#344 | Black Dog | Burnsville, MN | 1.8 TWh |
#345 | Mystic Generating Station | Charlestown, MA | 1.8 TWh |
#346 | Stanton Energy Center | Orlando, FL | 4.0 TWh |
#347 | Ferndale Generating Station | Ferndale, WA | 1.7 TWh |
#348 | Cunningham | Hobbs, NM | 1.7 TWh |
#349 | E C Gaston | Wilsonville, AL | 3.9 TWh |
#350 | Hopewell Cogeneration | Hopewell, VA | 1.7 TWh |
#351 | Beaver | Clatskanie, OR | 1.7 TWh |
#352 | Russell City Energy Center | Hayward, CA | 1.7 TWh |
#353 | Tiverton Power Plant | Tiverton, RI | 1.7 TWh |
#355 | Hay Road | Wilmington, DE | 1.6 TWh |
#356 | Valley (CA) | Sun Valley, CA | 1.6 TWh |
#357 | V H Braunig | Elmendorf, TX | 1.6 TWh |
#358 | Hot Spring Generating Facility | Malvern, AR | 1.6 TWh |
#359 | Pueblo Airport Generating Station | Pueblo, CO | 1.6 TWh |
#360 | Kendall Square Station | Cambridge, MA | 1.6 TWh |
#361 | River Road Gen Plant | Vancouver, WA | 1.6 TWh |
#362 | Theodore Cogen Facility | Theodore, AL | 1.6 TWh |
#363 | H Wilson Sundt Generating Station | Tucson, AZ | 1.6 TWh |
#364 | Motiva Enterprises Port Arthur Refinery | Port Arthur, TX | 1.7 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Arvah B Hopkins.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Apalachee | Marianna, FL | 140.7 GWh | 45.2 mi |
Bainbridge Solar | Bainbridge, GA | 2.0 GWh | 38 mi |
BE Solar LLC | Atlanta, GA | 5.0 GWh | 32.8 mi |
Blue Springs | Marianna, FL | 130.4 GWh | 46.4 mi |
Cairo Solar Farm, LLC | Cairo, GA | 3.5 GWh | 33.3 mi |
Cool Springs Solar (Hybrid) | Bainbridge, GA | 490.0 GWh | 26.4 mi |
CoTAL Solar Farm | Tallahassee, FL | 36.3 GWh | 5.7 mi |
Decatur County Solar Project | Bainbridge, GA | 41.6 GWh | 37.9 mi |
Decatur Parkway Solar Project, LLC | Bainbridge, GA | 171.6 GWh | 39.8 mi |
Falmouth Renewable Energy Center | Live Oak, FL | 56.3 GWh | 36.8 mi |
FL Solar 4, LLC | Tallahassee, FL | 64.3 GWh | 18.3 mi |
Fourmile Creek | Altha, FL | 111.7 GWh | 52.2 mi |
FPL Chipola River Solar Energy Center | Altha, FL | 130.7 GWh | 52.3 mi |
FPL Flowers Creek Solar Energy Center | Altha, FL | 116.6 GWh | 39 mi |
J Woodruff | Chattahoochee, FL | 224.2 GWh | 32.8 mi |
Oil Dri 2 Solar | Ochlocknee, GA | 2.9 GWh | 42.2 mi |
S O Purdom | St Marks, FL | 1.4 TWh | 23.3 mi |
Sub 12 | Tallahassee, FL | 15.6 GWh | 8.4 mi |
Walton Bainbridge Power Facility | Bainbridge, GA | 138.0 MWh | 32.9 mi |
Wild Azalea Solar Energy Center | Chattahoochee, FL | 168.6 GWh | 25.5 mi |