Arroyo Solar Energy Storage Hybrid
TBD, Pueblo Pintado, NM 87013Plant Summary Information
Arroyo Solar Energy Storage Hybrid is ranked #21 out of 5,655 solar farms nationwide in terms of total annual net electricity generation.
Arroyo Solar Energy Storage Hybrid generated 216.1 GWh during the 3-month period between June 2024 to September 2024.
Plant Name | Arroyo Solar Energy Storage Hybrid |
---|---|
Utility Name | Arroyo Solar LLC |
Location | McKinley County, NM |
Initial Operation Date | July 2023 |
Last Update | Sep 2024 |
Annual Generation | 653.6 GWh |
Annual Consumption | 2.4 M MMBtu |
Ranked #1,021 out of 11,852 Power Plants Nationwide | |
Ranked #21 out of 5,655 Solar Power Plants Nationwide | |
Ranked #18 out of 137 New Mexico Power Plants | |
Ranked #1 out of 83 New Mexico Solar Power Plants | |
Fuel Types | Solar |
Map of Arroyo Solar Energy Storage Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Arroyo Solar Energy Storage Hybrid.
Monthly Net Generation for Arroyo Solar Energy Storage Hybrid
Arroyo Solar Energy Storage Hybrid Details
Summary Information | |
---|---|
Plant Name | Arroyo Solar Energy Storage Hybrid (63172) |
Plant Address | TBD, Pueblo Pintado, NM 87013 |
Utility | Arroyo Solar LLC (62921) |
Latitude, Longitude | 35.97035, -107.56308 |
Generation Dates on File | Jul 2023 to Sep 2024 |
Initial Operation Date | July 2023 |
Annual Generation | 653.6 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | Public Service Company of New Mexico (PNM) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Public Service Co of NM (15473) NM |
Grid Voltage | 345.00 kV |
Energy Storage | Yes |
Generator ARESS Details Operating July 2023
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 150 MW |
Summer Capacity | 150 MW |
Winter Capacity | 150 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2023 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 600 |
---|---|
Maximum Charge Rate | 150 MW |
Maximum Discharge Rate | 150 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 150 |
Storage Enclosure Type | CS |
Arbitrage | P |
Independent | Yes |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Arroyo Solar Energy Storage Hybrid Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#11 | Solana Generating Station | Gila Bend, AZ | 823.1 GWh |
#12 | Juno Solar Project | Lamesa, TX | 793.4 GWh |
#13 | Prospero Solar | Andrews, TX | 747.8 GWh |
#14 | Neptune Energy Center Hybrid | Boone, CO | 701.6 GWh |
#15 | Solar Star 2 | Rosamond, CA | 708.8 GWh |
#16 | Copper Mountain Solar 5, LLC | Boulder City, NV | 691.5 GWh |
#17 | Slate Hybrid | Stratford, CA | 665.0 GWh |
#18 | IP Radian, LLC | Brookesmith, TX | 681.1 GWh |
#19 | Agua Caliente Solar Project | Dateland, AZ | 675.2 GWh |
#20 | Prospero Solar II | Andrews, TX | 675.0 GWh |
#22 | Texas Solar Nova 1 | Spur, TX | 666.4 GWh |
#23 | Desert Sunlight 300, LLC | Desert Center, CA | 659.4 GWh |
#24 | Arlington Energy Center II | Blythe, CA | 628.1 GWh |
#25 | Silver State Solar Power South | Primm Valley, NV | 650.9 GWh |
#26 | Mojave Solar Project | Hinkley, CA | 627.0 GWh |
#27 | California Valley Solar Ranch | California Valley, CA | 623.8 GWh |
#28 | Stateline Solar | Nipton, CA | 618.5 GWh |
#29 | Arrow Canyon Solar Hybrid | Moapa, NV | 607.5 GWh |
#30 | Copper Mountain Solar 3 | Boulder City, NV | 615.4 GWh |
#31 | Moapa Southern Paiute | Moapa, NV | 615.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Arroyo Solar Energy Storage Hybrid.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Abiquiu Dam | Abiquiu, NM | 47.8 GWh | 66.3 mi |
Bluewater CDEC 1 | Bluewater, NM | 6.8 GWh | 54.9 mi |
Bluffview | Farmington, NM | 278.9 GWh | 63.1 mi |
Cibola | Seboyeta, NM | 19.2 GWh | 56.1 mi |
City of Rio Rancho WWTP | Rio Rancho, NM | 2.6 GWh | 69.2 mi |
Cuba 2.5ac, LLC | Cuba, NM | 6.0 GWh | 34.7 mi |
El Vado Dam | Tierra Amarilla, NM | 1.9 GWh | 63.2 mi |
Encino Solar Energy Center | Rio Rancho Estates, NM | 142.2 GWh | 58.1 mi |
Grants CDEC 2 | Grants, NM | 12.2 GWh | 59.2 mi |
Jicarilla Solar 1 LLC | Dulce, NM | 66.9 GWh | 28.7 mi |
Jicarilla Solar 2 | Dulce, NM | 122.1 GWh | 24.9 mi |
Los Alamos PV Site | Los Alamos, NM | 526.0 MWh | 70.4 mi |
Navajo Dam | Farmington, NM | 91.4 GWh | 57.8 mi |
NMRD Data Center III, LLC | Rio Ranchero, NM | 138.0 GWh | 57.4 mi |
OE_ESCL | Grants, NM | 180.0 GWh | 48.5 mi |
Red Mesa Wind LLC | Seboyeta, NM | 201.1 GWh | 49.5 mi |
Rio Rancho High School | Rio Rancho, NM | 2.3 GWh | 70.1 mi |
Route 66 Energy Center, LLC | San Fidel, NM | 139.4 GWh | 60.3 mi |
Sandoval Solar Energy Center | Rio Rancho, NM | 15.6 GWh | 63.5 mi |
Sue Cleveland High School | Rio Rancho, NM | 2.1 GWh | 68.2 mi |