Altona
5003 Military Turnpike, Altona, NY 12910Plant Summary Information
Altona is ranked #21 out of 34 wind farms in New York in terms of total annual net electricity generation.
Altona generated 35.2 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | Altona |
---|---|
Utility Name | Valcour Operating Services, LLC |
Location | Clinton County, NY |
Initial Operation Date | April 2009 |
Last Update | Dec 2023 |
Annual Generation | 120.2 GWh |
Annual Consumption | 463.7 k MMBtu |
Ranked #2,952 out of 11,835 Power Plants Nationwide | |
Ranked #827 out of 1,343 Wind Power Plants Nationwide | |
Ranked #79 out of 832 New York Power Plants | |
Ranked #21 out of 34 New York Wind Power Plants | |
Fuel Types | Wind |
Previous Operator |
Noble Wind Operations LLC (2013 to 2019) Valcour Operating Services, LLC (2020 to 2023) |
Map of Altona
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Altona.
Monthly Net Generation for Altona
Altona Details
Summary Information | |
---|---|
Plant Name | Altona (56901) |
Plant Address | 5003 Military Turnpike, Altona, NY 12910 |
Utility | Valcour Operating Services, LLC (63858) |
Latitude, Longitude | 44.8216, -73.6509 |
Generation Dates on File | Apr 2009 to Dec 2023 |
Initial Operation Date | April 2009 |
Annual Generation | 120.2 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | New York Power Authority (15296) |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator 1 Details Operating April 2009
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Wholly Owned by Other Entity |
RTO ISO LMP Node Designation | 323606 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | 323606 |
Nameplate Capacity | 97.5 MW |
Summer Capacity | 97.5 MW |
Winter Capacity | 97.5 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2009 |
Combined Heat & Power | No |
---|---|
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 65 |
Planned New Prime Mover | WT |
Planned Energy Source | WND |
Planned New Nameplate Capacity | 97.5 MW |
Planned Repower | January 2026 |
Other Planned Modifications | No |
Turbine Details | |
Number Of Turbines | 65 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.5 SLE |
Design Wind Speed | 19 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 262 |
Altona Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Valcour Altona Windpark, LLC | 13860 Ballantyne Corporate Place Suite 300, Charlotte, NC 28277 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#817 | Great Plains Windpark LLC | Spearman, TX | 127.7 GWh |
#818 | Golden Hills North Wind Energy Center | Livermore, CA | 127.1 GWh |
#819 | Kawailoa Wind | Haleiwa, HI | 126.0 GWh |
#820 | Storm Lake II | Alta, IA | 125.6 GWh |
#821 | Cameron Ridge LLC | Mojave, CA | 125.1 GWh |
#822 | Ashtabula Wind Energy Center | Luverne, ND | 123.2 GWh |
#823 | Clinton | Churubusco, NY | 123.1 GWh |
#824 | Passadumkeag Windpark LLC | Greenbush, ME | 121.9 GWh |
#825 | Cambria Wind LLC | Sidman, PA | 121.6 GWh |
#826 | Palmer's Creek Wind Farm, LLC | Granite Falls, MN | 121.1 GWh |
#828 | Ridgetop | Mojave, CA | 119.5 GWh |
#829 | Beebe 1B | Ithaca, MI | 119.0 GWh |
#830 | Crofton Bluffs Wind LLC | Bloomfield, NE | 119.0 GWh |
#831 | Cabazon Wind Partners | Cabazon, CA | 118.0 GWh |
#832 | Linden Wind Energy Project | Goldendale, WA | 116.7 GWh |
#833 | Sterling I Wind Farm | Tatum, NM | 116.5 GWh |
#834 | Kimball Wind | Kimball, NE | 115.7 GWh |
#835 | Sandy Ridge Wind Farm | Tyrone, PA | 114.5 GWh |
#836 | Poseidon Wind, LLC | Herber, AZ | 113.2 GWh |
#837 | San Gorgonio Westwinds II LLC | North Palm Springs, CA | 112.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Altona.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Adirondack Solar | Ellenburg Center, NY | 1.6 GWh | 10.6 mi |
Boas Rd #1 Community Solar Farm | Mooers, NY | 3.0 GWh | 7.9 mi |
Boas Rd #2 Community Solar Farm | Mooers, NY | 3.0 GWh | 7.8 mi |
Boas Rd #3 Community Solar Farm | Mooers, NY | 2.7 GWh | 7.8 mi |
Boas Rd #4 Community Solar Farm | Mooers, NY | 2.6 GWh | 7.5 mi |
Cadyville | Town ofSchuyler Falls, NY | 26.3 GWh | 8.9 mi |
Chateaugay | Chateaugay, NY | 140.6 GWh | 19.2 mi |
Chateaugay High Falls Hydro | Chateaugay, NY | 2.8 GWh | 22.2 mi |
Clinton | Churubusco, NY | 123.1 GWh | 18.1 mi |
Clinton LFGTE Facility | Morrisonville, NY | 47.3 GWh | 9.4 mi |
County Route 11 Community Solar Farm | Mooers, NY | 5.9 GWh | 7.9 mi |
Ellenburg | Churubusco, NY | 111.3 GWh | 18.1 mi |
High Falls - Saranac NY | Town of Saranac, NY | 88.5 GWh | 13.5 mi |
Lower Saranac Hydroelectric Facility | Plattsburgh, NY | 32.7 GWh | 12.7 mi |
Marble River Wind Farm | Churubusco, NY | 364.7 GWh | 17.3 mi |
Mill C | Town of Plattsburgh, NY | 29.1 GWh | 8.8 mi |
Rainbow Falls Auscble | Town of Auscble, NY | 9.8 GWh | 22.6 mi |
Route 22 Community Solar Farm CSG | Plattsburgh, NY | 5.9 GWh | 11.2 mi |
Saranac Facility | Plattsburgh, NY | 234.4 GWh | 12.2 mi |
VEC Alburgh Array | Alburgh, VT | 1.2 GWh | 20.8 mi |