A G Wishon
County Road 222, North Fork, CA 93643Plant Summary Information
A G Wishon is ranked #140 out of 222 hydroelectric power plants in California in terms of total annual net electricity generation.
A G Wishon is comprised of 4 generators and generated 1.8 GWh during the 3-month period between September 2023 to December 2023.
Plant Name | A G Wishon |
---|---|
Utility Name | Pacific Gas & Electric Co. |
Location | Madera County, CA |
Initial Operation Date | September 1910 |
Last Update | Dec 2023 |
Annual Generation | 16.1 GWh |
Annual Consumption | 61.6 k MMBtu |
Ranked #5,314 out of 11,835 Power Plants Nationwide | |
Ranked #825 out of 1,371 Water Power Plants Nationwide | |
Ranked #745 out of 1,569 California Power Plants | |
Ranked #140 out of 222 California Water Power Plants | |
Fuel Types | Water |
Previous Operator |
Pacific Gas & Electric Co (2013 to 2016) Pacific Gas & Electric Co. (2017 to 2023) |
Map of A G Wishon
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for A G Wishon.
Monthly Net Generation for A G Wishon
A G Wishon Details
Summary Information | |
---|---|
Plant Name | A G Wishon (293) |
Plant Address | County Road 222, North Fork, CA 93643 |
Utility | Pacific Gas & Electric Co. (14328) |
Latitude, Longitude | 37.15105, -119.50472 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | September 1910 |
Annual Generation | 16.1 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | North & South Forks Willow Cre |
Ash Impoundment | No |
Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
Grid Voltage | 70.00 kV |
Energy Storage | No |
Generator 1 Details Operating September 1910
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WISHON_6_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WISHON_6_UNITS-APND |
Nameplate Capacity | 3.2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1910 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 2 Details Operating September 1910
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WISHON_6_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WISHON_6_UNITS-APND |
Nameplate Capacity | 3.2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1910 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 3 Details Operating September 1910
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WISHON_6_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WISHON_6_UNITS-APND |
Nameplate Capacity | 3.2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1910 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 4 Details Operating September 1910
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
RTO ISO LMP Node Designation | WISHON_6_UNITS-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | WISHON_6_UNITS-APND |
Nameplate Capacity | 3.2 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 5 MW |
Winter Capacity | 5 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1910 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
A G Wishon Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#815 | Parishville | Parishville, NY | 16.6 GWh |
#816 | Soda | Soda Springs, ID | 16.5 GWh |
#817 | West Delaware Tunnel Plant | Grahamsville, NY | 16.5 GWh |
#818 | Thermalito Diverson Dam | Oroville, CA | 16.5 GWh |
#819 | Hoist | Negaunee, MI | 16.3 GWh |
#820 | Basalt | Aspen, CO | 16.3 GWh |
#821 | Granite Shoals | Marble Falls, TX | 16.3 GWh |
#822 | Island Park | Island Park, ID | 16.3 GWh |
#823 | Errol Hydroelectric Project | Errol, NH | 16.2 GWh |
#824 | Point A | Andalusia, AL | 16.1 GWh |
#826 | Warrensburg Hydroelectric | Warrensburg, NY | 16.1 GWh |
#827 | Weybridge | Weybridge, VT | 16.0 GWh |
#828 | Brule | Florence, WI | 16.0 GWh |
#829 | Moyie Springs | Moyie Springs, ID | 16.0 GWh |
#830 | High Falls (WI) | Town of Stephenson, WI | 16.0 GWh |
#831 | Waterbury 22 | Waterbury, VT | 15.9 GWh |
#832 | Gateway | Mountain Green, UT | 15.9 GWh |
#833 | James R Smith | Marquette, MI | 15.8 GWh |
#834 | Tri-County Water Hydropower Project | Ridgway, CO | 15.8 GWh |
#835 | Tunnel 1 Power Project | Nyssa, OR | 15.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding A G Wishon.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Big Creek 1 | Big Creek, CA | 393.8 GWh | 15.1 mi |
Big Creek 2 | Auberry, CA | 296.2 GWh | 11.4 mi |
Big Creek 2A | Auberry, CA | 537.5 GWh | 11.4 mi |
Big Creek 3 | Auberry, CA | 783.0 GWh | 6.5 mi |
Big Creek 4 | North Fork, CA | 452.9 GWh | 1.2 mi |
Big Creek 8 | Auberry, CA | 152.9 GWh | 10.5 mi |
Clovis East High School | Clovis, CA | 1.4 GWh | 25.4 mi |
Clovis High School | Clovis, CA | 1.3 GWh | 25.1 mi |
Clovis North High School | Fresno, CA | 1.4 GWh | 22.1 mi |
Friant Hydro Facility | Friant, CA | 106.2 GWh | 15.2 mi |
J S Eastwood | Shaver Lake, CA | 3.8 GWh | 13.7 mi |
Kerckhoff 2 | Auberry, CA | 357.0 GWh | 6.2 mi |
Kings River PH | Balch Camp, CA | 206.7 GWh | 26.3 mi |
Mammoth Pool | North Fork, CA | 561.8 GWh | 10.4 mi |
Pine Flat | Piedra, CA | 561.7 GWh | 24.1 mi |
Portal | Lakeshore, CA | 21.2 GWh | 20.4 mi |
Saint Agnes Medical Center | Fresno, CA | 26.1 GWh | 26.2 mi |
San Joaquin 2 | North Fork, CA | 1.5 GWh | 3.6 mi |
SCCCD - Clovis Community College | Fresno, CA | 2.0 GWh | 22.2 mi |
Site 980 65 | Madera, CA | 6.3 GWh | 22.7 mi |