PacifiCorp West
Balancing Authority Summary Information
PacifiCorp West is ranked #49 out of 65 balancing authorities in terms of total annual electricity generation.
Balancing Authority | PacifiCorp West |
---|---|
States | California Oregon Washington |
Last Update | Nov 2024 |
Annual Generation | 5.2 TWh |
Power Plants | 128 |
Utilities | 70 |
Ranked #49 out of 65 in terms of net annual generation | |
Ranked #25 out of 47 in terms of annual generation from water | |
Power Plant Types | Water | 40.9% Wind | 34% Solar | 18% Other Fuel | 6.7% |
Map of PacifiCorp West
Register Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for PacifiCorp West.
Daily Net Generation for PacifiCorp West for the past 3 Years
Plant Name | Utility | Location | Annual Generation | Plant Date | Last Update | Fuel Types |
---|---|---|---|---|---|---|
Bend | PacifiCorp | Bend, OR | 83 MWh | Jun 1913 | Dec 2023 | Water |
Prospect 1 | PacifiCorp | Prospect, OR | 219 MWh | Dec 1911 | Dec 2022 | Water |
C-Drop Hydro | C-Drop | Klamath Falls, OR | 1 GWh | Apr 2012 | Sep 2023 | Water |
Oregon University System Rabbit Field | Tesla Inc. | Corvallis, OR | 1 GWh | Feb 2014 | Dec 2023 | Solar |
Wallowa Falls | PacifiCorp | Joseph, OR | 2 GWh | Jun 1921 | Nov 2023 | Water |
Oregon Convention Center | Tesla Inc. | Portland, OR | 2 GWh | Jun 2016 | Dec 2023 | Solar |
Sprague Hydro | Sprague Hydro LLC | Bly, OR | 2 GWh | Sep 1989 | Dec 2023 | Water |
Blue Skies Solar, LLC | Blue Skies Solar, LLC | Arvin, CA | 2 GWh | Nov 2021 | Dec 2023 | Solar |
Bakersfield 111 | Bakersfield 111 LLC | Bakersfield, CA | 2 GWh | Jun 2015 | Dec 2023 | Solar |
Oregon University System OIT Klamath Falls | Tesla Inc. | Klamath Falls, OR | 2 GWh | Dec 2013 | Dec 2023 | Solar |
Orchard Avenue 1 | Yakima-Tieton Irrigation Dist | Yakima, WA | 3 GWh | Feb 1987 | Oct 2023 | Water |
Adapture CA2, LLC | Adapture Renewables, Inc. | Orland, CA | 3 GWh | Feb 2016 | Dec 2023 | Solar |
Big Top LLC | Odessa Energy Services LLC | Echo, OR | 3 GWh | May 2009 | Dec 2023 | Wind |
Cowiche | Yakima-Tieton Irrigation Dist | Tieton, WA | 3 GWh | Feb 1987 | Oct 2023 | Water |
Black Cap Solar Plant | PacifiCorp | Lakeview, OR | 4 GWh | Sep 2012 | Dec 2023 | Solar |
Lacomb Irrigation District | Lacomb Irrigation Dist | Lebanon, OR | 4 GWh | Nov 1986 | Dec 2023 | Water |
45 Mile Hydroelectric Project | EBD Hydro LLC | Culver, OR | 5 GWh | Apr 2015 | Oct 2023 | Water |
Roseburg LFG | Roseburg LFG Energy LLC | Roseburg, OR | 6 GWh | Nov 2011 | Dec 2023 | Landfill Gas |
Klamath Falls Solar 2 CSG | MN8 Energy LLC | Klamath Falls, OR | 6 GWh | Nov 2017 | Dec 2023 | Solar |
Wagon Trail LLC | Odessa Energy Services LLC | Echo, OR | 6 GWh | May 2009 | Dec 2023 | Wind |
Peters Drive Plant | Farmer's Irrigation District | Hood River, OR | 6 GWh | Oct 1987 | Dec 2023 | Water |
Fall Creek | PacifiCorp | Hornbrook, CA | 7 GWh | Aug 1903 | Dec 2023 | Water |
Old Mill Solar | Old Mill Solar | Bly, OR | 7 GWh | Nov 2015 | Dec 2023 | Solar |
Foothill Sanitary Landfill - Solar Array | Ameresco San Joaquin Solar LLC | Linden, CA | 8 GWh | Dec 2020 | Dec 2022 | Solar |
NorWest Energy 4, LLC | MN8 Energy LLC | Bonanza, OR | 10 GWh | Dec 2018 | Dec 2023 | Solar |
Butter Creek Power LLC | Odessa Energy Services LLC | Echo, OR | 10 GWh | May 2009 | Dec 2023 | Wind |
Juniper Ridge Hydroelectric Project | Central Oregon Irrigation Dist | Bend, OR | 11 GWh | Sep 2010 | Dec 2023 | Water |
Slate Creek | Central Rivers Power US, LLC | Lakehead, CA | 11 GWh | Apr 1990 | Dec 2023 | Water |
Dorena Hydro-Electric Facility | Dorena Hydro, LLC | Cottage Grove, OR | 11 GWh | May 2014 | Dec 2023 | Water |
NorWest Energy 9 LLC | MN8 Energy LLC | Pendleton, OR | 11 GWh | Aug 2018 | Dec 2023 | Solar |
Dry Creek LFG to Energy Project | Oregon Environmental Industries LLC | Eagle Point, OR | 13 GWh | Jun 2007 | Dec 2023 | Landfill Gas |
Falls Creek | Eagle Creek Renewable Energy, LLC | Cascadia, OR | 14 GWh | Nov 1984 | Dec 2023 | Water |
Ward Butte Windfarm LLC | Echo 1 | Echo, OR | 14 GWh | May 2009 | Dec 2023 | Wind |
Eagle Point | PacifiCorp | Eagle Point, OR | 15 GWh | Oct 1957 | Dec 2023 | Water |
Siphon Power Project | Central Oregon Irrigation Dist | Bend, OR | 16 GWh | Jul 1989 | Dec 2023 | Water |
Copper Dam Plant | Farmer's Irrigation District | Hood River, OR | 16 GWh | Dec 1985 | Dec 2023 | Water |
Pacific Canyon Windfarm LLC | Echo 1 | Echo, OR | 16 GWh | May 2009 | Dec 2023 | Wind |
BC Solar | BC Solar | Lakeview, OR | 17 GWh | Oct 2016 | Dec 2023 | Solar |
Four Corners Windfarm LLC | Echo 2 | Echo, OR | 17 GWh | May 2009 | Dec 2023 | Wind |
Douglas County Forest Products | Douglas County Forest Products | Roseburg, OR | 17 GWh | Nov 2006 | Dec 2023 | Wood/Wood Waste Solids |
Four Mile Canyon Windfarm LLC | Echo 2 | Echo, OR | 17 GWh | May 2009 | Dec 2023 | Wind |
Box Canyon Dam | Siskiyou Power Authority | Mount Shasta, CA | 17 GWh | May 1986 | Dec 2023 | Water |
Woodline Solar | Woodline Solar, LLC | Dairy, OR | 17 GWh | Nov 2017 | Dec 2023 | Solar |
OR Solar 5, LLC | Heelstone Energy Holdings, LLC | Merrill, OR | 18 GWh | Dec 2017 | Dec 2023 | Solar |
Eagle Point Solar | Norwest Energy 7, LLC | Central Point, OR | 18 GWh | Nov 2017 | Dec 2023 | Solar |
Bly Solar Center | GCL New Energy, Inc. | Bly, OR | 18 GWh | Nov 2018 | Dec 2023 | Solar |
Fish Creek | PacifiCorp | Idleyld Park, OR | 18 GWh | May 1952 | Dec 2023 | Water |
NorWest Energy 2, LLC | Cypress Creek Renewables | Bend, OR | 19 GWh | Nov 2016 | Aug 2024 | Solar |
Tumbleweed Solar, LLC | Heelstone Energy Holdings, LLC | Redmond, OR | 19 GWh | Nov 2017 | Dec 2023 | Solar |
Chiloquin Solar, LLC | Heelstone Energy Holdings, LLC | Chiloquin, OR | 19 GWh | Dec 2017 | Dec 2023 | Solar |
Sand Ranch Windfarm LLC | Echo 1 | Echo, OR | 19 GWh | May 2009 | Dec 2023 | Wind |
Threemile Canyon | Threemile Canyon Wind I, LLC | Boardman, OR | 20 GWh | Jun 2009 | Dec 2023 | Wind |
Adams Solar Center | GCL New Energy, Inc. | Madras, OR | 20 GWh | Jun 2018 | Dec 2023 | Solar |
Oregon Trail Windfarm LLC | Echo 1 | Echo, OR | 21 GWh | May 2009 | Dec 2023 | Wind |
OR Solar 2, LLC | OR Solar 2, LLC | Eagle Point, OR | 21 GWh | Sep 2020 | Dec 2023 | Solar |
Bear Creek Solar Center | GCL New Energy, Inc. | Bend, OR | 22 GWh | Aug 2018 | Dec 2023 | Solar |
Elbe Solar Center | GCL New Energy, Inc. | Madras, OR | 22 GWh | Jul 2018 | Dec 2023 | Solar |
Schumann Wind Farm | Chopin Wind, LLC | Milton-Freewater, OR | 22 GWh | Oct 2022 | Dec 2023 | Wind |
Short Mountain | Emerald People's Utility Dist | Eugene, OR | 22 GWh | Jan 1992 | Dec 2023 | Landfill Gas |
OSLH, LLC | OSLH, LLC | Bend, OR | 22 GWh | Nov 2016 | Dec 2023 | Solar |
Garrett Solar | SOLV Energy LLC | Lakeview, OR | 23 GWh | Nov 2019 | Dec 2023 | Solar |
OR Solar 3, LLC | Heelstone Energy Holdings, LLC | Malin, OR | 23 GWh | Nov 2017 | Dec 2023 | Solar |
OR Solar 6, LLC | Heelstone Energy Holdings, LLC | Lakeview, OR | 23 GWh | Nov 2017 | Dec 2023 | Solar |
OR Solar 8, LLC | Heelstone Energy Holdings, LLC | Dairy, OR | 24 GWh | Feb 2018 | Dec 2023 | Solar |
Opal Springs Hydro | Deschutes Valley Water District | Culver, OR | 24 GWh | Dec 1984 | Dec 2023 | Water |
Clearwater 1 | PacifiCorp | Idleyld Park, OR | 25 GWh | May 1953 | Dec 2023 | Water |
Orchard Windfarm 1, LLC | Orchard Windfarm, LLC | Lexington, OR | 26 GWh | Nov 2020 | Dec 2023 | Wind |
Orchard Windfarm 4, LLC | Orchard Windfarm, LLC | Lexington, OR | 26 GWh | Nov 2020 | Dec 2023 | Wind |
Chopin Wind LLC | Chopin Wind, LLC | Milton-Freewater, OR | 26 GWh | Sep 2016 | Dec 2023 | Wind |
Clearwater 2 | PacifiCorp | Idleyld Park, OR | 26 GWh | Oct 1953 | Dec 2023 | Water |
Threemile Digester | TMF Biofuels, LLC | Boardman, OR | 38 GWh | Nov 2012 | Dec 2023 | Natural Gas |
Evergreen BioPower LLC | Evergreen BioPower LLC | Lyons, OR | 38 GWh | Aug 2007 | Dec 2023 | Wood/Wood Waste Solids |
Soda Springs | PacifiCorp | Idleyld Park, OR | 40 GWh | Feb 1952 | Dec 2023 | Water |
Tieton Dam Hydro Electric Project | City of Burbank Water and Power | Rimrock, WA | 45 GWh | Aug 2006 | Oct 2023 | Water |
Slide Creek | PacifiCorp | Idleyld Park, OR | 48 GWh | Jun 1951 | Dec 2023 | Water |
Warm Springs Power Enterprises | Warm Springs Power Enterprises | Warm Springs, OR | 57 GWh | May 1982 | Dec 2023 | Water |
Roseburg Forest Products Biomass | Roseburg Forest Products | Weed, CA | 57 GWh | Nov 1989 | Dec 2023 | Wood/Wood Waste Solids |
Copco 1 | PacifiCorp | Hornbrook, CA | 71 GWh | Dec 1917 | Dec 2023 | Water |
Combine Hills I | Eurus Combine Hills I LLC | Milton-Freewater, OR | 73 GWh | Nov 2003 | Dec 2023 | Wind |
Iron Gate | PacifiCorp | Hornbrook, CA | 82 GWh | Jan 1962 | Dec 2023 | Water |
Skysol | Skysol Holdco LLC | Merrill, OR | 86 GWh | Nov 2023 | Aug 2024 | Solar |
Copco 2 | PacifiCorp | Hornbrook, CA | 87 GWh | Jun 1925 | May 2023 | Water |
Lemolo 1 | PacifiCorp | Idleyld Park, OR | 89 GWh | Jun 1955 | Dec 2023 | Water |
Prineville Solar Energy LLC | Invenergy Services LLC | Prineville, OR | 91 GWh | Jan 2021 | Aug 2024 | Solar |
Airport Solar | Airport Solar LLC | Lakeview, OR | 101 GWh | Nov 2019 | Aug 2024 | Solar |
Dillard Complex | Roseburg Forest Products Co | Dillard, OR | 114 GWh | Dec 1954 | Dec 2023 | Wood/Wood Waste Solids : 99.2% Natural Gas : 0.8% |
Lemolo 2 | PacifiCorp | Toketee Falls, OR | 118 GWh | Oct 1956 | Dec 2023 | Water |
Solar Star Oregon II | Avangrid Renewables LLC | Prineville, OR | 124 GWh | Sep 2017 | Aug 2024 | Solar |
Biomass One LP | Biomass One LP | White City, OR | 136 GWh | Nov 1985 | Dec 2023 | Wood/Wood Waste Solids |
Millican Solar Energy LLC | Invenergy Services LLC | Prineville, OR | 139 GWh | Feb 2021 | Aug 2024 | Solar |
Prospect 2 | PacifiCorp | Prospect, OR | 163 GWh | Dec 1927 | Dec 2023 | Water |
Toketee Falls | PacifiCorp | Idleyld Park, OR | 166 GWh | Nov 1949 | Dec 2023 | Water |
John C Boyle | PacifiCorp | Keno, OR | 192 GWh | Sep 1958 | Dec 2023 | Water |
Lost Creek | USACE Northwestern Division | Trail, OR | 221 GWh | Aug 1977 | Dec 2023 | Water |
Vansycle II Wind Energy Center | FPL Energy Stateline II Inc | Athena, OR | 329 GWh | Nov 2009 | Dec 2023 | Wind |
Merwin | PacifiCorp | Ariel, WA | 472 GWh | Jun 1931 | Dec 2023 | Water |
Yale | PacifiCorp | Amboy, WA | 517 GWh | Aug 1953 | Dec 2023 | Water |
Marengo Wind Plant | PacifiCorp | Dayton, WA | 561 GWh | Jul 2007 | Dec 2023 | Wind |
Swift 1 | PacifiCorp | Cougar, WA | 568 GWh | Nov 1958 | Aug 2024 | Water |
Hermiston Generating Plant | Hermiston Generating Co LP | Hermiston, OR | 3 TWh | May 1996 | Aug 2024 | Natural Gas |
Surrounding Balancing Authorities
Rank | Balancing Authority | Annual Net Generation | # Power Plants |
---|---|---|---|
#40 | Avangrid Renewables, LLC | 9.1 TWh | 19 |
#16 | Bonneville Power Administration | 80.0 TWh | 158 |
#58 | City of Tacoma, Department of Public Utilities, Light Division | 2.2 TWh | 9 |
#30 | Gridforce Energy Management, LLC | 18.2 TWh | 1 |
#36 | Idaho Power Company | 15.2 TWh | 164 |
#44 | Portland General Electric Company | 7.8 TWh | 95 |
#46 | Public Utility District No. 1 of Chelan County | 7.2 TWh | 3 |
#43 | Public Utility District No. 2 of Grant County, Washington | 7.9 TWh | 4 |
#45 | Puget Sound Energy, Inc. | 7.7 TWh | 36 |
#50 | Seattle City Light | 4.6 TWh | 9 |
Balancing Authorities with Similar Net Generation
Rank | Balancing Authority | Annual Net Generation | # Power Plants |
---|---|---|---|
#44 | Portland General Electric Company | 7.8 TWh | 95 |
#45 | Puget Sound Energy, Inc. | 7.7 TWh | 36 |
#46 | Public Utility District No. 1 of Chelan County | 7.2 TWh | 3 |
#47 | El Paso Electric Company | 6.4 TWh | 31 |
#48 | Imperial Irrigation District | 5.7 TWh | 65 |
#49 | PacifiCorp West | 5.2 TWh | 128 |
#50 | Seattle City Light | 4.6 TWh | 9 |
#51 | Duke Energy Progress West | 4.1 TWh | 10 |
#52 | Arlington Valley, LLC | 3.6 TWh | 1 |
#53 | Southwestern Power Administration | 3.5 TWh | 31 |