Balancing Authority of Northern California
Balancing Authority Summary Information
Balancing Authority of Northern California is ranked #35 out of 65 balancing authorities in terms of total annual electricity generation.
Balancing Authority | Balancing Authority of Northern California |
---|---|
States | California |
Last Update | Nov 2024 |
Annual Generation | 15.2 TWh |
Power Plants | 83 |
Utilities | 32 |
Ranked #35 out of 65 in terms of net annual generation | |
Ranked #30 out of 53 in terms of annual generation from natural gas | |
Power Plant Types | Natural Gas | 54.8% Water | 39.7% Solar | 4.6% Other Fuel | 0.7% |
Map of Balancing Authority of Northern California
Register Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Balancing Authority of Northern California.
Daily Net Generation for Balancing Authority of Northern California for the past 3 Years
Plant Name | Utility | Location | Annual Generation | Plant Date | Last Update | Fuel Types |
---|---|---|---|---|---|---|
Shasta | U S Bureau of Reclamation | Redding, CA | 2 TWh | May 1944 | Aug 2024 | Water |
Keswick | U S Bureau of Reclamation | Redding, CA | 373 GWh | Sep 1949 | Aug 2024 | Water |
Nimbus | U S Bureau of Reclamation | Folsom, CA | 70 GWh | Apr 1955 | Dec 2023 | Water |
Folsom | U S Bureau of Reclamation | Folsom, CA | 649 GWh | Apr 1955 | Aug 2024 | Water |
Jaybird | Sacramento Municipal Util Dist | Camino, CA | 462 GWh | Mar 1961 | Aug 2024 | Water |
Judge F Carr | U S Bureau of Reclamation | French Gulch, CA | 215 GWh | Apr 1963 | Aug 2024 | Water |
Camino | Sacramento Municipal Util Dist | Camino, CA | 307 GWh | Sep 1963 | Aug 2024 | Water |
Union Valley | Sacramento Municipal Util Dist | Fresh Pond, CA | 168 GWh | Sep 1963 | Dec 2023 | Water |
Spring Creek | U S Bureau of Reclamation | Redding, CA | 307 GWh | Dec 1963 | Aug 2024 | Water |
Trinity | U S Bureau of Reclamation | Weaverville, CA | 356 GWh | Jan 1964 | Aug 2024 | Water |
Robbs Peak | Sacramento Municipal Util Dist | Fresh Pond, CA | 69 GWh | Sep 1965 | Dec 2023 | Water |
White Rock/Slab Creek | Sacramento Municipal Util Dist | Placerville, CA | 495 GWh | Jan 1968 | Aug 2024 | Water |
Loon Lake | Sacramento Municipal Util Dist | Fresh Pond, CA | 126 GWh | Aug 1971 | Dec 2023 | Water |
New Melones | U S Bureau of Reclamation | Jamestown, CA | 511 GWh | May 1979 | Aug 2024 | Water |
McClure | Modesto Irrigation District | Modesto, CA | 1 GWh | Jun 1980 | Dec 2023 | Natural Gas : 61.0% Distillate Fuel Oil : 39.0% |
Jones Fork | Sacramento Municipal Util Dist | Fresh Pond, CA | 29 GWh | May 1985 | Dec 2023 | Water |
McClellan (CA) | Sacramento Municipal Util Dist | Sacramento, CA | 3 GWh | Feb 1986 | Dec 2023 | Natural Gas |
Roseville Power Plant #2 | City of Roseville - (CA) | Rocklin, CA | 4 GWh | Mar 1986 | Dec 2023 | Natural Gas : 99.9% |
Whiskeytown | City of Redding - (CA) | Whiskeytown, CA | 24 GWh | Aug 1986 | Dec 2023 | Water |
Redding Power | City of Redding - (CA) | Redding, CA | 330 GWh | Dec 1988 | Aug 2024 | Natural Gas |
Woodland | Modesto Irrigation District | Modesto, CA | 301 GWh | Oct 1993 | Aug 2024 | Natural Gas |
Carson Ice-Gen Project | Sacramento Municipal Util Dist | Sacramento, CA | 71 GWh | Sep 1995 | Aug 2024 | Natural Gas : 99.9% |
SCA Cogen 2 | Sacramento Municipal Util Dist | Sacramento, CA | 599 GWh | Feb 1997 | Aug 2024 | Natural Gas |
SPA Cogen 3 | Sacramento Municipal Util Dist | Sacramento, CA | 632 GWh | Nov 1997 | Aug 2024 | Natural Gas |
Kiefer Landfill | Sacramento County of Dpt Waste | Sloughhouse, CA | 67 GWh | Nov 1999 | Dec 2023 | Landfill Gas |
Cosumnes | Sacramento Municipal Util Dist | Herald, CA | 4 TWh | Jan 2006 | Aug 2024 | Natural Gas : 98.8% Other Biomass Gas : 1.2% |
Ripon Generation Station | Modesto Irrigation District | Ripon, CA | 10 GWh | May 2006 | Dec 2023 | Natural Gas |
Roseville Energy Park | City of Roseville - (CA) | Roseville, CA | 425 GWh | Oct 2007 | Aug 2024 | Natural Gas |
Aerojet I | Altus Power America Management, LLC | Rancho Cordova, CA | 6 GWh | Nov 2009 | Dec 2023 | Solar |
Aerojet II | Altus Power America Management, LLC | Rancho Cordova, CA | 4 GWh | May 2010 | Dec 2023 | Solar |
Intel Folsom | Tesla Inc. | Folsom, CA | 1 GWh | Jun 2010 | Dec 2023 | Solar |
Depot Park Solar System | Depot Park Solar Farm | Sacramento, CA | 2 GWh | Nov 2010 | Dec 2023 | Solar |
SMUD at Fleshman | Sacramento PV Energy, LLC | Galt, CA | 4 GWh | Nov 2011 | Dec 2023 | Solar |
SMUD at Van Conett | Sacramento PV Energy, LLC | Galt, CA | 1 GWh | Nov 2011 | Dec 2023 | Solar |
SMUD at Grundman | Sacramento PV Energy, LLC | Elk Grove, CA | 24 GWh | Nov 2011 | Dec 2023 | Solar |
SMUD at Lawrence | Sacramento PV Energy, LLC | Elk Grove, CA | 4 GWh | Nov 2011 | Dec 2023 | Solar |
RE Dillard 1 LLC | MN8 Energy LLC | Sloughhouse, CA | 6 GWh | Dec 2011 | Dec 2023 | Solar |
RE Kammerer 1 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Dec 2011 | Dec 2023 | Solar |
RE Dillard 2 LLC | MN8 Energy LLC | Sloughhouse, CA | 6 GWh | Dec 2011 | Dec 2023 | Solar |
RE Dillard 3 LLC | MN8 Energy LLC | Sloughhouse, CA | 6 GWh | Dec 2011 | Dec 2023 | Solar |
RE Bruceville 1 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Dec 2011 | Dec 2023 | Solar |
RE Kammerer 2 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Jan 2012 | Dec 2023 | Solar |
RE Bruceville 2 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Jan 2012 | Dec 2023 | Solar |
RE Kammerer 3 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Jan 2012 | Dec 2023 | Solar |
RE Bruceville 3 LLC | MN8 Energy LLC | Elk Grove, CA | 11 GWh | Jan 2012 | Dec 2023 | Solar |
Solar Star California II LLC | Solar Star California II LLC | Sacramento, CA | 3 GWh | Jul 2012 | Dec 2023 | Solar |
Green Acres Solar Facility 1 | SIT Renewables, Inc. | Elk Grove, CA | 5 GWh | Aug 2012 | Dec 2023 | Solar |
Green Acres Solar Facility 2 | SIT Renewables, Inc. | Elk Grove, CA | 2 GWh | Aug 2012 | Dec 2023 | Solar |
Intel Folsom Phase 2 | Tesla Inc. | Folsom, CA | 2 GWh | Sep 2012 | Dec 2023 | Solar |
RE McKenzie 1 LLC | MN8 Energy LLC | Galt, CA | 12 GWh | Oct 2012 | Dec 2023 | Solar |
RE McKenzie 2 LLC | MN8 Energy LLC | Galt, CA | 11 GWh | Oct 2012 | Dec 2023 | Solar |
RE McKenzie 3 LLC | MN8 Energy LLC | Galt, CA | 12 GWh | Oct 2012 | Dec 2023 | Solar |
RE McKenzie 4 LLC | MN8 Energy LLC | Galt, CA | 12 GWh | Oct 2012 | Dec 2023 | Solar |
RE McKenzie 5 LLC | MN8 Energy LLC | Galt, CA | 11 GWh | Oct 2012 | Dec 2023 | Solar |
RE McKenzie 6 LLC | MN8 Energy LLC | Galt, CA | 11 GWh | Oct 2012 | Dec 2023 | Solar |
FAA NorCal TRACON | Enfinity NorCal 1 FAA LLC | Mather AFB, CA | 1 GWh | Nov 2012 | Dec 2023 | Solar |
Sacramento Fairbain Water Treatment Plant | Tesla Inc. | Sacramento, CA | 1 GWh | Jan 2013 | Dec 2023 | Solar |
Strata Roof 1 | Strata Manager, LLC | Sacramento, CA | 2 GWh | Apr 2013 | Dec 2023 | Solar |
Sacramento (SMUD) | Terraform Arcadia | Sacramento, CA | 2 GWh | Jul 2014 | Dec 2023 | Solar |
Intel Folsom Phase 3 | Tesla Inc. | Folsom, CA | 9 GWh | Mar 2016 | Dec 2023 | Solar |
Rancho Seco Solar, LLC | Rancho Seco Solar, LLC | Herald, CA | 13 GWh | Jul 2016 | Dec 2023 | Solar |
Amazon - Patterson PV | AES Distributed Energy | Patterson, CA | 2 GWh | Apr 2017 | Dec 2023 | Solar |
Dept of General Services -FTB | California PV Energy 2, LLC | Sacramento, CA | 5 GWh | Jun 2017 | Dec 2023 | Solar |
Sacramento Regional County Sanitation PV | Tesla Inc. | Elk Grove, CA | 7 GWh | Nov 2017 | Dec 2023 | Solar |
US GSA - Sacramento | Tesla Inc. | Sacramento, CA | 2 GWh | Feb 2018 | Dec 2023 | Solar |
Chambers 4 - Sacramento SMF1 | MN8 Energy LLC | Sacramento, CA | 4 GWh | Aug 2018 | Dec 2023 | Solar |
Folsom SP and CSP Sacramento | Ecoplexus, Inc | Represa, CA | 611 MWh | Apr 2019 | Dec 2023 | Solar |
Blue Shld Of Cal- El Dorado Hlls Mtr B | Tesla Inc. | El Dorado Hills, CA | 3 GWh | Jun 2019 | Dec 2023 | Solar |
Department of Justice | Ecoplexus, Inc | Sacramento, CA | 4 GWh | Mar 2020 | Dec 2023 | Solar |
Renew Solar ABC Sacramento LLC | Greenbacker Renewable Energy Corporation | Sacramento, CA | 3 GWh | Oct 2020 | Dec 2023 | Solar |
Sacramento Point West Medical Offices | KP Sacramento Point West Medical Offices Solar, LLC | Sacramento, CA | 2 GWh | Oct 2020 | Dec 2023 | Solar |
Wildflower Solar 1 | Lightsource Renewable Energy Asset Management, LLC | Elverta, CA | 29 GWh | Nov 2020 | Dec 2023 | Solar |
Rancho Seco Solar II, LLC | Rancho Seco Solar II, LLC | Twin Cities, CA | 251 GWh | Jan 2021 | Aug 2024 | Solar |
Rancho Cordova Medical Offices | KP Rancho Cordova Medical Offices Solar, LLC | Rancho Cordova, CA | 2 GWh | Mar 2021 | Dec 2023 | Solar |
Surrounding Balancing Authorities
Rank | Balancing Authority | Annual Net Generation | # Power Plants |
---|---|---|---|
#40 | Avangrid Renewables, LLC | 9.1 TWh | 19 |
#16 | Bonneville Power Administration | 80.0 TWh | 158 |
#7 | California Independent System Operator | 191.5 TWh | 1,943 |
#30 | Gridforce Energy Management, LLC | 18.2 TWh | 1 |
#36 | Idaho Power Company | 15.2 TWh | 164 |
#33 | Los Angeles Department of Water and Power | 15.9 TWh | 120 |
#22 | Nevada Power Company | 37.6 TWh | 136 |
#49 | PacifiCorp West | 5.2 TWh | 128 |
#44 | Portland General Electric Company | 7.8 TWh | 95 |
#57 | Turlock Irrigation District | 2.3 TWh | 11 |
Balancing Authorities with Similar Net Generation
Rank | Balancing Authority | Annual Net Generation | # Power Plants |
---|---|---|---|
#30 | Gridforce Energy Management, LLC | 18.2 TWh | 1 |
#31 | South Carolina Public Service Authority | 17.9 TWh | 33 |
#32 | Florida Municipal Power Pool | 17.3 TWh | 21 |
#33 | Los Angeles Department of Water and Power | 15.9 TWh | 120 |
#34 | Public Service Company of New Mexico | 15.5 TWh | 108 |
#35 | Balancing Authority of Northern California | 15.2 TWh | 83 |
#36 | Idaho Power Company | 15.2 TWh | 164 |
#37 | Tucson Electric Power | 14.6 TWh | 51 |
#38 | Seminole Electric Cooperative | 14.1 TWh | 5 |
#39 | JEA | 9.5 TWh | 22 |